Skill stanislavnianko/product-discovery-claude-skills/plugins/discovery-phase/skills/estimation

Curated Claude skill pack for structured product discovery

Install
npx -y skills add stanislavnianko/product-discovery-claude-skills --skill estimation

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 1 stars1 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

What its author says it does

Copied from the file, not written here

[discovery-phase pack · scoping] Translates a defined scope into an effort estimate broken down by discipline (Dev / QA / BA / PM / Design) × phase, with confidence intervals and explicit assumptions. Designed to feed proposal and sow-draft. Produces estimation.md. Reads discovery-context.md and scope-doc.md.

SKILL.md

5.3 KB, as published. Nobody here has run it

Estimation

Part of the discovery-phase skill pack · scoping group · reads discovery-context.md (run profile-builder first if missing).

Agency-style estimation: effort by discipline × phase, with low / expected / high ranges, and a list of assumptions that, if violated, invalidate the estimate. The output is the heart of any commercial proposal.

Step 1 — Read context

Read discovery-context.md (sections 1. Client → Stage, 3. Engagement → Mode and Budget context, 6. Constraints) and scope-doc.md.

If discovery-context.md is missing, ask the BA inline: "(a) greenfield or migration; (b) fixed-fee or T&M?" — tag the output [ASSUMED ENGAGEMENT]. If scope-doc.md is missing, ask for in/out scope bullets per area, or fall back to a class-of-magnitude estimate (S / M / L / XL) tagged [NO-SCOPE] — not for client use without a follow-up proper estimate. Never block; recommend profile-builder / feature-scoping for high-stakes work.

Step 2 — Pick estimation method

Match to engagement timeline + scope size:

MethodWhenEffort to produce
3-point parametricStandard for proposals; S/M/L scopes30-60 min
Bottom-up by user storyDetailed scope, large engagement2-4 hours
Reference-class ("we did X for Y, multiply by Z")Repeat engagement, similar scope15-30 min
Phased gatesLong engagement; only first phase precise30 min for phase 1, range for rest

Default to 3-point parametric for discovery-phase outputs.

Step 3 — Discipline × Phase matrix

Build the matrix. Adapt phases to engagement mode:

Phase \ DisciplineBAPMDesignDev (FE)Dev (BE)QADevOpsTotal
Discovery follow-ups
Design (wireframe → high-fi)
Build phase 1
Build phase 2
QA / hardening
Launch / handoff
Total per discipline

Numbers are person-hours or person-days. Pick one unit and stick to it.

Step 4 — Three-point ranges

For every cell with non-trivial effort, capture:

  • Low — best case, no surprises
  • Expected — most likely
  • High — top 10% case (NOT worst case — worst case is "kill")

Total each row and column. Sum row totals = sum of column totals = grand total (sanity check).

Step 5 — Apply uncertainty multipliers

Per discipline, apply a multiplier reflecting estimate confidence:

ConfidenceMultiplier on Expected
Done this exact thing before1.0
Familiar pattern, slight variation1.2
Familiar tech, new domain1.5
New tech + new domain2.0
Bleeding edge / heavy R&D3.0

Show both raw and adjusted totals.

Step 6 — Assumptions that invalidate the estimate

A bullet list of what must be true. If any becomes false, the estimate is void and re-estimation is required.

Typical:

  • Scope-doc remains stable (no mid-build scope additions)
  • Client provides decisions within 2 business days
  • Existing tech stack: <X>
  • Auth uses existing SSO (no new identity provider)
  • Data volume below <N>
  • Third-party APIs: <list> available with documented contracts
  • Design assets / brand guidelines provided by client
  • Single time zone overlap of 4+ hours daily

Step 7 — Risk-driven contingency

Pull from risk-assumption-map.md (if present) the rows tagged [agency] or [shared]. For each, add a contingency line item:

RiskIf realized, additional effortOwner

This becomes the basis for proposal "contingency budget" or T&M risk-pool conversations.

Step 8 — Format for downstream skills

Format the output so proposal can pull headline numbers + assumption list verbatim, and sow-draft can pull the matrix + risk register.

Output

./discovery/estimation.md per ./template.md.

Append to _log.md: [estimation | YYYY-MM-DD] method: <method>; total: <hours/days>; multiplier: <Xx>; contingency: <Y%>.

Anti-patterns

  • Single-number estimate. Always 3-point. Stakeholders read the single number as a commitment.
  • No assumption list. An estimate without listed assumptions = a commitment. Different commercial implications.
  • Padding via vague "buffer". Be specific: "+20% because new domain", not "+20% buffer".
  • Estimating by hours when budget is in days. Match the unit the client thinks in.
  • Hiding contingency. If risks are real, name them with their cost. Hidden buffers fund themselves with worse risks later.
  • Estimating without a scope-doc. Strongly preferred to run feature-scoping first; if you proceed via inline bootstrap, the estimate inherits any vagueness in the bullets — keep it tagged DRAFT-ONLY until a real scope doc exists.