Agile Sprint planning assistant that builds actionable plans by selecting scope based on team capacity and historical velocity, breaking down stories into estimated tasks, analyzing dependencies, and balancing workloads. Triggers when a user asks for Sprint Planning, iteration scoping, story/task assignment, workload balancing, dependency analysis, or team capacity calculation.From its SKILL.md

Install
npx -y skills add serejaris/kimi-skills --skill sprint-plan-builder

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 5 stars5 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

What its file declares

Copied from the file, not written here

The file declares its own license as MIT. That is the author’s claim about this one file, and it is not the same thing as the license GitHub reports for the repository, which is listed with the other numbers below.

SKILL.md

11.3 KB, ~2.6k tokens by cl100k_base, as published. Nobody here has run it

Sprint Plan Builder — Agile Sprint Planning

Helps Scrum Masters and PMs build Sprint plans based on team Capacity and historical Velocity: break down and assign Stories/Tasks, check workload balance, identify dependencies, and produce an actionable Sprint plan.


SOP Overview

Step 1: Gather Inputs → Step 2: Calculate Team Capacity → Step 3: Define Sprint Goal & Scope
    → Step 4: Task Breakdown & Estimation → Step 5: Dependency Analysis → Step 6: Task Assignment & Workload Balancing
    → Step 7: Output Sprint Plan → Step 8: Risk Review & Commitment Check

Step 1: Gather Input Information

Collect the following from the user (proactively ask for any missing items):

InputDescriptionExample
Sprint DurationIteration length in working days2 weeks (10 working days)
Team RosterName + RoleAlice (Frontend), Bob (Backend), Carol (QA)
Availability per MemberAccount for PTO, meetings, other project commitmentsAlice 8 days, Bob 10 days, Carol 9 days
Historical VelocityCompleted story points from the last 3–5 Sprints[32, 28, 35, 30, 33]
Product BacklogStories to be planned (with priority and estimates)See Backlog table
Known DependenciesPredecessor/successor relationships between StoriesStory-3 depends on Story-1

Defaults When Information Is Missing

  • Sprint Duration not specified → default to 2 weeks (10 working days)
  • Availability not specified → default to Sprint Duration × 0.8 (accounting for meetings and overhead)
  • Historical Velocity unknown → use 70% of the current total estimate as a conservative target
  • Role not specified → treat as a general developer

Step 2: Calculate Team Capacity

2.1 Individual Capacity

Individual Capacity = Available Days × Effective Hours per Day × Focus Factor
ParameterDefaultDescription
Effective Hours per Day6 hours8-hour workday minus meetings, breaks, etc.
Focus Factor0.8Accounts for context switching, communication overhead

2.2 Total Team Capacity

Total Team Capacity (person-hours) = Σ(Individual Capacity of each member)
Total Team Capacity (story points) = Derived from Velocity reference

2.3 Capacity Calculation Example

MemberAvailable DaysEffective Hrs/DayFocus FactorIndividual Capacity (hrs)
Alice860.838.4
Bob1060.848.0
Carol960.843.2
Total129.6

Step 3: Define Sprint Goal & Scope

3.1 Velocity Reference Calculation

Reference Velocity = Average Velocity over the last N Sprints
Recommended N = 3–5, excluding clear outliers
MethodUse CaseDescription
Simple AverageStable teammean(last 3–5 Sprints)
Weighted AverageRecent team changesHigher weight for recent Sprints
MinimumConservative commitmentmin(last 3 Sprints)

3.2 Scope Selection Rules

  1. Sort the Backlog by priority from highest to lowest
  2. Accumulate story points until approaching but not exceeding the reference Velocity
  3. If adding the last Story would exceed 110% of Velocity, exclude it
  4. Reserve 10–15% buffer for contingencies and technical debt

Step 4: Task Breakdown & Estimation

4.1 Story Breakdown Check

Each Story should satisfy the INVEST criteria:

CriterionMeaningCheckpoint
IndependentSelf-containedCan it be delivered on its own?
NegotiableFlexibleIs the implementation approach flexible?
ValuableValuableDoes it deliver clear value to users?
EstimableEstimableCan the team provide a point estimate?
SmallSmallCan it be completed within one Sprint?
TestableTestableAre acceptance criteria clearly defined?

4.2 Estimation Reference

If the user has not provided estimates, use the following reference table:

Story PointsComplexityTypical Effort
1TrivialA few hours, no discussion needed
2SimpleHalf a day to one day, clear approach
3Low-Medium1–2 days, minor uncertainty
5Medium2–3 days, requires design and discussion
8Complex3–5 days, spans multiple components
13Very ComplexAbout one week, consider splitting
21+Too LargeMust be split before planning

Step 5: Dependency Analysis

5.1 Dependency Types

TypeDescriptionExample
Finish-to-Start (FS)B cannot start until A finishesFrontend integration starts after API development
Start-to-Start (SS)B can start after A startsBackend development can begin once DB design starts
External DependencyDepends on delivery outside the teamWaiting for a third-party API spec
Technical DependencyDepends on a technical component or environmentCore framework must be set up first

5.2 Dependency Review Process

  1. List all prerequisites for each Story
  2. Build a dependency graph (represented as a list or matrix)
  3. Identify the critical path: find the longest dependency chain
  4. Flag risky dependencies:
    • External dependencies (uncontrollable) → mark as High Risk
    • Cross-member dependency chains > 3 → mark as Medium Risk
    • Circular dependencies → must be resolved

5.3 Dependency Matrix Output Format

| Story    | Depends On  | Depended On By | Type     | Risk |
|----------|-------------|----------------|----------|------|
| Story-1  | None        | Story-3        | -        | Low  |
| Story-2  | None        | None           | -        | Low  |
| Story-3  | Story-1     | Story-5        | FS       | Med  |
| Story-4  | External API| Story-5        | External | High |
| Story-5  | Story-3, 4  | None           | FS       | High |

Step 6: Task Assignment & Workload Balancing

6.1 Assignment Principles

  1. Skill Match First: Match members' skills to Story technical requirements
  2. Dependency Order: Assign depended-upon Stories first to avoid blocking downstream work
  3. Workload Balance: Keep each member's load within ±20% of the team average
  4. Avoid Single Points of Failure: Critical Stories should not be assigned to only one person

6.2 Workload Balance Calculation

Member Load % = Assigned Story Points / Individual Capacity (SP equivalent) × 100%
Team Average Load % = Total Assigned SP / Total Team Capacity (SP equivalent) × 100%
Load Deviation = |Member Load % - Team Average Load %|

6.3 Workload Balance Checks

CheckThresholdAction
Member Load > 100%OverloadedMust reassign tasks to other members
Member Load > 90%HighWarning — no buffer
Member Load < 50%LowCheck if they can take on more work
Load Deviation > 20%ImbalancedRebalance assignments
One person > 40% of total SPOver-concentratedSpread the risk

6.4 Rebalancing Strategies

When workload is imbalanced, adjust in this priority order:

  1. Move lower-priority Stories from overloaded members to underloaded ones
  2. Reassign Stories with flexible skill requirements
  3. Split large Stories so multiple people can work in parallel
  4. Reduce Sprint scope (remove the lowest-priority Stories)

Step 7: Output the Sprint Plan

After completing the steps above, produce output using the following template:

## Sprint Plan: Sprint [Number] ([Start–End Dates])

### Sprint Goal
[One sentence describing the core objective of this Sprint]

### Team Capacity

| Member | Role | Available Days | Capacity (hrs) |
|--------|------|---------------|----------------|

- Total Team Capacity: X person-hours
- Reference Velocity: X story points
- This Sprint: X story points (X% of Velocity)

### Story Assignments

| # | Story | Priority | Points | Owner | Dependencies | Status |
|---|-------|----------|--------|-------|--------------|--------|

### Workload Distribution

| Member | Assigned SP | Load % | Status |
|--------|-------------|--------|--------|

### Dependencies

[Dependency matrix or dependency chain description]

### Critical Path
[List the longest dependency chain and expected completion order]

### Risks & Notes
- [Risk item 1]
- [Risk item 2]
- [Buffer and contingency plans]

Step 8: Risk Review & Commitment Check

Final Checklist

After producing the plan, confirm each item:

  • Are total story points within 80–100% of Velocity?
  • Is each member's load between 60–90%?
  • Is load deviation ≤ 20%?
  • Are there any circular dependencies? (Not allowed)
  • Are external dependencies flagged with a risk level?
  • Is someone assigned to every Story on the critical path?
  • Is a 10–15% buffer reserved?
  • Are any Story estimates above 13 points? (Should be split)
  • Does any single member carry more than 40% of total story points?

Common Issues & Recommendations

IssueRecommendation
Insufficient Velocity dataUse a conservative estimate (80% of the lowest known value)
Team member changesCount new members at 50% capacity for their first Sprint
Unclear requirementsAdd a Spike (technical investigation) for unclear Stories; do not count toward Velocity
Accumulated technical debtReserve 15–20% capacity per Sprint for tech debt
Cross-team dependenciesFlag as external dependency; align with the other team in advance

Common Pitfalls (Must Check During Planning)

PitfallConsequenceCorrect Approach
Treating Velocity as a hard ceiling and filling 100%No buffer; any surprise derails the SprintReserve 10–15% buffer; commit to 85–90%
Using full working days for capacity, ignoring meetings and PTOInflated capacity; actual delivery falls shortAlways use Available Days × 6h × 0.8
Skipping dependency analysis and jumping to assignmentBlockers discovered mid-Sprint, forcing reworkBuild the dependency matrix before assigning
Including large Stories (>13 SP) without splittingInaccurate estimates, untrackable progressStories above 13 points must be split first
Placing the entire critical path on one personSingle point of failure; one sick day breaks the chainSpread critical-path tasks across 2+ people
Assigning full capacity to new team membersNewcomers ramp up slowly, actual output falls shortCount new members at 50% capacity for Sprint 1

References

  • Mike Cohn, Agile Estimating and Planning
  • Scrum Guide 2020 (scrumguides.org)
  • SAFe (Scaled Agile Framework) — PI Planning and Sprint Planning methodology
  • PMI-ACP (Agile Certified Practitioner) body of knowledge