Activity duration estimation
Skill Ldxs001/workbuddy-skills/skills/activity-duration-estimation
一个包含agent和skill的集合:RAG、技能审查、周报生成、项目管理、质量监控...及技术方案/内部设计文档
npx -y skills add Ldxs001/workbuddy-skills --skill activity-duration-estimationAssembled from the repository path, not quoted from the project. Check it against their README if it does not work.
One thing to look at
- 2 stars2 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.
What its author says it does
Copied from the file, not written here
活动历时估算 + WBS工作分解 + 项目文档生成 + 经济效益分析 + 挣值管理(Activity Duration Estimation & WBS & Project Docs & Economic Analysis & EVM)—— 支持三点估算/蒙特卡洛四种方法 + WBS项目规划与分解 + 项目文档双模式生成(手动空模版/逐节自动)+ ROI/NPV/IRR/BCR 经济效益分析 + PV/EV/AC/SPI/CPI 挣值管理。三库隔离架构:shared.db + economic.db + evm.db。输出自包含HTML评估报告、经济效益分析报告和挣值分析报告。
The file declares its own license as MIT. That is the author’s claim about this one file, and it is not the same thing as the license GitHub reports for the repository, which is listed with the other numbers below.
SKILL.md
14.2 KB, as published. Nobody here has run it
activity-duration-estimation — 全周期项目管理
WBS项目规划 → 活动历时估算 → 项目文档生成,三环节完整闭环。 全流程由
scripts/runner.py的run_full()自动编排, LLM 只需调用一个函数即可完成项目从分解到文档的全部工作。 详细内容拆分到references/*.md按需加载。
触发场景
正向触发:估算工期/三点估算/PERT/蒙特卡洛/β分布/OMP/紧前关系/FS-SS-FF-SF/CPM甘特图/重叠分析/P50-P90/生成评估报告:估算工期/三点估算/PERT/蒙特卡洛/β分布/OMP/紧前关系/FS-SS-FF-SF/CPM甘特图/重叠分析/P50-P90/生成评估报告
不触发:仅概念询问 / 纯数学讨论 / 明确使用其他技能
核心能力
📚 渐进式加载:本技能采用渐进式 MD 体系,
SKILL.md为入口(≤230行),详细内容拆分到references/*.md按需加载。
| # | 能力 | 说明 |
|---|---|---|
| 0 | WBS工作分解 (子技能) | 基于3个参考模板+LLM自适应填充,支持4种分解方法,100%规则验证,自动衔接估算 |
| 1 | 项目文档生成 (子技能) | 双模式:手动模式输出特化空模版(token≈0)/ 自动模式逐节生成,4个预置模板(立项/结项/相关方/风险) |
| 2 | 四种估算方法 | 直接估算法 / β分布(PERT)估算法 / 正态分布估算法 / 蒙特卡洛模拟法 |
| 3 | 语义分析推荐 | 根据任务类型(建筑/制造/软件/科研/农业等)自动推荐最适估算方法组合 |
| 4 | 外部知识搜索 | 两阶段搜索流程:大模型自判→搜索补充→汇总推荐 |
| 5 | 知识库查询/写入 (新增) | 按需信息通道,与联网搜索平行。标准字段硬编码,LLM做格式翻译入库。支持历史项目查询、OMP基准检索、外部数据库/文件(SQLite/CSV/MD/DOCX/JSON)按标准导入 |
| 6 | CPM关键路径分析 | 基于紧前关系的关键路径计算,含ES/EF/LS/LF/总时差,自动识别关键任务 |
| 7 | 多分布蒙特卡洛 | 支持PERT-Beta、三角分布、泊松近似三种分布并行模拟,提供多维度概率评估 |
| 8 | 任务重叠分析 | 自动检测任务时间重叠,输出最大重叠数和最长重叠时段 |
| 9 | 甘特图可视化 | 基于CPM结果的甘特图(SVG),关键路径高亮标注 |
| 10 | 紧前关系规划 | 手动指定/自动规划两种模式,支持FS/SS/FF/SF四种依赖关系 |
| 11 | HTML评估报告 | 自包含HTML,含甘特图/概率分布/重叠分析图表,有图有表有数据有分析 |
| 12 | 项目文档生成 | 双模式:手动空模版/混合逐节生成;4个P0模板(立项/结项/相关方/风险) |
| 13 | 全局配置系统 | 5项可调整配置(联网搜索/知识库采集/知识库调用/文档指定/文档撰写),每项可选 auto/manual。scripts/settings_server.py 提供 HTML 可视化配置面板。配置通过 state.settings 注入流程,LLM 可读取 _get_setting() 决定行为。 |
| 14 | 经济效益分析 (分支子技能) | 独立于全流程,单独触发。ROI/NPV/IRR/BCR/PBP 计算引擎 + HTML 报告 + 独立 economic.db 知识库。可插入立项申请书模板。 |
| 15 | 挣值管理 (分支子技能) | 独立于全流程,单独触发。PV/EV/AC/SPI/CPI/EAC 计算引擎 + HTML 报告 + 独立 evm.db 知识库。可插入结项报告书模板。 |
渐进式文件索引
| 文件名 | 分类 | 包含内容 | 审计关联 |
|---|---|---|---|
references/antipatterns.md | 规范指南 | skill 编写中的常见反模式。包含:错误做法示例、正确做法示例、避坑指引。 | R-18 |
references/changelog.md | 版本管理 | 版本更新日志。包含:版本号、更新类型、修复项、升级说明。 | R-24 |
references/economic-analysis-methodology.md | 参考文档 | > 子技能定位:独立于活动历时估算的核心全流程,单独触发、单独运行。 | 无 |
references/evm-methodology.md | 参考文档 | > 子技能定位:独立于活动历时估算的核心全流程,单独触发、单独运行。 | 无 |
references/faq.md | 常见问题 | 常见疑问与解答。包含:问题分类、原因分析、解决方案。 | R-19, R-25 C-19 |
references/knowledge-interface.md | 参考文档 | > 知识库是与「联网搜索」平行的信息获取/存储通道。 | 无 |
references/methods.md | 参考文档 | > 本文件详细说明四种活动历时估算方法的公式、计算步骤和适用场景。 | 无 |
references/permissions.md | 权限与测试 | 权限扫描说明与测试结论。包含:风险等级、高权限操作说明、测试概览、计时统计。 | R-15, R-16 |
references/project-docs-methodology.md | 参考文档 | > 本文件说明:project-docs 子技能的双模式设计、模板结构、操作流程和使用规范。 | 无 |
references/report-template.md | 参考文档 | > 本文件定义 REPORT_DATA 数据结构的完整接口,以及分析结果→格式化→填充→生成的标准化流程。 | 无 |
references/risk-dimensions.md | 参考文档 | > 内置7大类风险维度,根据项目特征自动匹配适用维度。 | 无 |
references/search-integration.md | 参考文档 | > 本文件说明外部知识搜索的两个阶段流程。 | 无 |
references/semantic-analysis.md | 参考文档 | > 本文件说明语义分析引擎如何工作:任务参数提取、任务类型分类、推荐方法映射。 | 无 |
references/thinking-tools.md | 参考文档 | > 本文件收录项目管理/文档撰写中常用的思维工具和方法论框架。 | 无 |
references/wbs-methodology.md | 参考文档 | > 本文件定义 WBS(Work Breakdown Structure)在活动历时估算技能中的完整实现:分解方法、参考模板、递归算法、验证规则以及与估算流程的 | 无 |
工作流程
工作流程由 scripts/runner.py 自动编排,LLM 无需关心内部阶段顺序。
# 推荐:一键全流程(WBS → 估算 → 报告 → 文档,全环节必做)
from scripts.runner import run_full, PipelineState
result = run_full("帮我规划并估算一个电商后台管理系统")
if result["status"] == "ok":
state = result["state"]
print(state.wbs_text_tree) # ① WBS文本树
print(state.estimate_summary) # ② 估算摘要
print(state.html_report_path) # ③ HTML报告路径
print(state.doc_content) # ④ 项目文档
elif result["status"] == "blocked":
# 需要LLM提供WBS数据(即使已有OMP参数,WBS也是必做的)
wbs_data = {"name": "电商后台", "children": [...]} # LLM提供
state = PipelineState("帮我规划并估算一个电商后台管理系统")
state.run_wbs(custom_data=wbs_data)
result = state.run_full() # 继续执行估算→报告→文档
else:
print(result["message"]) # 错误信息
全流程阶段(代码硬编码,不可跳过,与 runner.py 中 6 个阶段一一对应):
- WBS分解 →
run_wbs()(全流程模式下必做,LLM提供结构化数据) - WBS进入估算门控 →
_wbs_passes_estimation_gate()硬校验 - 紧前关系规划 →
_prompt_llm_for_dependencies()/ 自动FS串联 - 估算计算 →
run_estimate()(全Python自动:CPM + MC + 重叠分析) - HTML评估报告 →
_generate_html_report()(全Python自动) - 项目文档 →
generate_docs()(按模板生成立项/结项/风险/相关方文档)
单独调用模式(不经过run_full()全流程,按需使用):
| 需求 | 调用方式 |
|---|---|
| 仅有估算需求 | run_pipeline(mode="estimate") 或 state.run_estimate() |
| 仅需文档 | run_pipeline(mode="docs") 或 state.generate_docs() |
| 仅WBS分解 | run_pipeline(mode="wbs") 或 state.run_wbs() |
LLM交互点
当流程需要LLM推理时,runner.py 会抛出 LLMInteractionRequired 异常:
| 交互点 | 触发条件 | LLM需提供 |
|---|---|---|
_prompt_llm_for_wbs() | 模糊需求 | WBS结构化数据 {name, children: [...]} |
_prompt_llm_for_omp() | 阶段缺OMP | OMP值 {o, m, p} |
_prompt_llm_for_dependencies() | >5个阶段 | 紧前关系或确认自动规划 |
LLM看到异常后按提示提供数据,然后继续执行即可。
快速开始
场景1:直接估算 — "乐观3天、最可能6天、悲观15天" → β分布7天, σ=2天 → 68%概率5~9天
场景2:多阶段CPM — "前端(5/10/20)→后端(8/15/25)→测试(10/20/35), FS" → 总工期47天 →出HTML报告
场景3:搜索辅助 — "装配式建筑施工" → 搜索同类→给出典型OMP→确认→估算
场景4:WBS→估算 — "帮我规划并估算电商后台" → 分解→确认→HTML报告
场景5:项目文档 — "生成立项申请书, 手动模式" → 空模板→"自动填充背景"→逐节生成→拼合
场景6:经济效益分析 — "初始100万, 年收益12万, 年支出5万, 5年, 终值200万, 折现率10%" → NPV=50.72, IRR=20.35%
场景7:挣值管理 — "项目到D阶段, 做挣值分析" → EV=320.27, SPI=1.01, CPI=1.07, EAC=379.73
常用操作速查
| 我想... | 一句话答案 |
|---|---|
| 快速估算一个项目工期 | 调用 from scripts.runner import run_full; result = run_full("项目描述") — AI 自动拆解+估算+出报告 |
| 只用 WBS 不做估算 | state.run_wbs() — 只做工作分解,不进估算流程 |
| 指定每个任务的 OMP | 在 WBS 数据结构中填写 {"o": 3, "m": 5, "p": 8} 字段 |
| 用我自己的文档模板 | load_template() → customize_sections() → save_template() — 增删改排章节后另存 |
| 更新全局配置 | python scripts/settings_manager.py set <key> <value> — 纯 CLI,无需 LLM 参与 |
| HTML 报告打不开 | 报告是自包含 HTML,直接用浏览器打开 state.html_report_path |
| 调整蒙特卡洛模拟次数 | run_full(mc_iterations=5000) — 默认 2000,数值越高越精确但越慢 |
| 从历史项目参考数据 | 告诉 LLM「查一下同类项目的基准数据」— 会自动搜索 SQLite 知识库 |
WBS子技能 — Phase -1:项目规划与工作分解
|
scripts/wbs_engine.py全流程模式下必做,由run_full()自动触发。
项目文档生成子技能 — :project-docs
|
scripts/project_docs_engine.py三种模式:manual(空模板,token≈0)/mixed(按章节设 auto/outline/manual,推荐)/全自动(所有节 auto)。 支持模板定制:增/删/改/重排章节、每节独立模式、另存为新模板。
from project_docs_engine import set_section_mode
tpl = load_template("立项申请书")
tpl = set_section_mode(tpl, "项目背景", "auto") # 自动生成
tpl = set_section_mode(tpl, "预算", "manual") # 留空手动填
state.generate_docs(mode="mixed", filled_sections={"project_background": "..."})
save_template(tpl, "我的模板", overwrite=True) # 另存自定义模板
内置模板:立项申请书(11节) / 结项报告书(10节) / 相关方登记册(4节) / 风险登记册(5节)
子模块详解
各子模块详细说明见 references/:
- Phase 0: 语义分析与方法推荐 →
references/semantic-analysis.md - Phase 1: 外部知识搜索 →
references/search-integration.md - Phase 2-3: 紧前关系规划 + 估算计算(CPM/MC/重叠分析)→
references/methods.md - Phase 4: HTML评估报告 →
references/report-template.md - WBS方法论: →
references/wbs-methodology.md - 项目文档: →
references/project-docs-methodology.md
| 估算方法 | 公式 | 适用场景 |
|---|---|---|
| 三点直接 | (O+M+P)/3 | 快速估算 |
| β分布(PERT) | (O+4M+P)/6, σ=(P-O)/6 | 标准项目管理 |
| 蒙特卡洛 | 2000+次模拟, 多分布并行 | 高不确定性项目 |
限制与边界
| 维度 | 说明 |
|---|---|
| 任务数量 | 建议 ≤50 个阶段/任务,超过时蒙特卡洛模拟耗时显著增加 |
| OMP值 | 必须满足 O ≤ M ≤ P(乐观≤最可能≤悲观),不满足时会提示修正 |
| 紧前关系 | 不能形成循环依赖(A→B→C→A),系统会检测并报错 |
| 工期单位 | 统一使用同一单位(天/小时/周),混用需先归一化 |
| 网络依赖 | 首次使用需联网搜索(非典型任务),后续使用完全离线 |
| 报告生成 | 输出自包含HTML文件,需要浏览器打开查看,不支持PDF直接导出 |