Sprint plan

Skill tranhieutt/software_development_department/.claude/skills/sprint-plan

Software Development Department

Install
npx -y skills add tranhieutt/software_development_department --skill sprint-plan

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

What its author says it does

Copied from the file, not written here

Generates or updates sprint plans with task breakdowns, capacity estimates, dependencies, and risk flags based on milestone goals and past velocity. Use when starting a new sprint, updating sprint progress, or checking sprint status.

SKILL.md

5.1 KB, ~1.1k tokens by cl100k_base, as published. Nobody here has run it

When this skill is invoked:

  1. Read the current milestone from production/milestones/.

  2. Read the previous sprint (if any) from production/sprints/ to understand velocity and carryover. Use Glob("production/sprints/*.md") then read the file with the highest sprint number.

  3. Scan design documents in design/ for features tagged as ready for implementation.

  4. Check the risk register at production/risk-register/ if it exists.

For new:

  1. Determine sprint number — count existing files in production/sprints/ and increment by 1. Sprint N = number of existing sprint files + 1.

  2. Generate a sprint plan following this format, then save to production/sprints/sprint-{N}.md (confirm path with user before writing):

# Sprint [N] -- [Start Date] to [End Date]

## Sprint Goal
[One sentence describing what this sprint achieves toward the milestone]

## Capacity
- Total days: [X]
- Buffer (20%): [Y days reserved for unplanned work]
- Available: [Z days]

## Tasks

### Must Have (Critical Path)
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

### Should Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

### Nice to Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

## Carryover from Previous Sprint
| Task | Reason | New Estimate |
|------|--------|-------------|

## Risks
| Risk | Probability | Impact | Mitigation |
|------|------------|--------|------------|

## Dependencies on External Factors
- [List any external dependencies]

## Definition of Done for this Sprint
- [ ] All Must Have tasks completed
- [ ] All tasks pass acceptance criteria
- [ ] No S1 or S2 bugs in delivered features
- [ ] Design documents updated for any deviations
- [ ] Code reviewed and merged

For update:

  1. Identify the current sprint file — find the latest file in production/sprints/ (highest sprint number). Read it.

  2. Ask the user which task(s) to update: task ID, new status (done / in-progress / blocked), and any notes or blocker details.

  3. Edit the sprint file in place using the Edit tool:

    • Move completed tasks to the "Completed" section if tracking status inline
    • Add blocker info to the Blocked table
    • Update % Done estimates for in-progress tasks
  4. Append a brief update log at the bottom of the file:

    ## Update Log
    - [YYYY-MM-DD]: [Summary of changes made]
    
  5. Confirm the edit to the user: "Sprint {N} updated — {X} task(s) changed."

For status:

  1. Generate a status report:
# Sprint [N] Status -- [Date]

## Progress: [X/Y tasks complete] ([Z%])

### Completed
| Task | Completed By | Notes |
|------|-------------|-------|

### In Progress
| Task | Owner | % Done | Blockers |
|------|-------|--------|----------|

### Not Started
| Task | Owner | At Risk? | Notes |
|------|-------|----------|-------|

### Blocked
| Task | Blocker | Owner of Blocker | ETA |
|------|---------|-----------------|-----|

## Burndown Assessment
[On track / Behind / Ahead]
[If behind: What is being cut or deferred]

## Emerging Risks
- [Any new risks identified this sprint]

Agent Consultation

For comprehensive sprint planning, consider consulting:

  • producer agent for capacity planning, risk assessment, and cross-department coordination
  • product-manager agent for feature prioritization and design readiness assessment

Protocol

  • Question: Reads mode from argument (new / update / status); update mode asks which tasks changed
  • Options: Skip — mode drives execution path
  • Decision: update mode — user specifies task IDs, new status, and blocker details
  • Draft: Plan or status report shown in conversation before writing
  • Approval: "May I write to production/sprints/sprint-[N].md?"

Output

Deliver exactly:

  • new: Sprint file saved to production/sprints/sprint-[N].md with Must Have / Should Have / Nice to Have tasks, estimates, and risks
  • update: In-place edit to current sprint file + update log entry appended
  • status: Status report with progress %, completed/in-progress/blocked tables, and burndown assessment
  • Next action: One sentence on what the team should do immediately