Scope check
Skill tranhieutt/software_development_department/.claude/skills/scope-check
Software Development Department
npx -y skills add tranhieutt/software_development_department --skill scope-checkAssembled from the repository path, not quoted from the project. Check it against their README if it does not work.
What its author says it does
Copied from the file, not written here
Analyzes a feature or sprint for scope creep by comparing current scope against the original plan, flagging additions and recommending cuts. Use when a sprint feels bloated or when the user mentions scope creep, scope check, or feature bloat.
SKILL.md
3.8 KB, 829 tokens by cl100k_base, as published. Nobody here has run it
When this skill is invoked:
-
Read the original plan — Find the relevant document:
- If a feature name: read the design doc from
design/docs/ - If a sprint number: read the sprint plan from
production/sprints/ - If a milestone: read the milestone definition from
production/milestones/
- If a feature name: read the design doc from
-
Read the current state — Check what has actually been implemented or is in progress:
- Scan the codebase for files related to the feature/sprint
- Read git log for commits related to this work
- Check for TODO comments that indicate unfinished scope additions
-
Compare original vs current scope:
## Scope Check: [Feature/Sprint Name] Generated: [Date] ### Original Scope [List of items from the original plan] ### Current Scope [List of items currently implemented or in progress] ### Scope Additions (not in original plan) | Addition | Who Added | When | Justified? | Effort | |----------|-----------|------|------------|--------| | [item] | [commit/person] | [date] | [Yes/No/Unclear] | [S/M/L] | ### Scope Removals (in original but dropped) | Removed Item | Reason | Impact | |-------------|--------|--------| | [item] | [why removed] | [what's affected] | ### Bloat Score - Original items: [N] - Current items: [N] - Items added: [N] (+[X]%) - Items removed: [N] - Net scope change: [+/-N] ([X]%) ### Risk Assessment - **Schedule Risk**: [Low/Medium/High] — [explanation] - **Quality Risk**: [Low/Medium/High] — [explanation] - **Integration Risk**: [Low/Medium/High] — [explanation] ### Recommendations 1. **Cut**: [Items that should be removed to stay on schedule] 2. **Defer**: [Items that can move to a future sprint/version] 3. **Keep**: [Additions that are genuinely necessary] 4. **Flag**: [Items that need a decision from producer/creative-director] -
Output the scope check with a clear verdict:
- On Track: Scope within 10% of original
- Minor Creep: 10-25% scope increase — manageable with adjustments
- Significant Creep: 25-50% scope increase — need to cut or extend timeline
- Out of Control: >50% scope increase — stop and re-plan
Rules
- Scope creep is additions without corresponding cuts or timeline extensions
- Not all additions are bad — some are discovered requirements. But they must be acknowledged and accounted for.
- When recommending cuts, prioritize preserving the core user experience over nice-to-haves
- Always quantify scope changes — "it feels bigger" is not actionable, "+35% items" is
Protocol
- Question: Reads feature name, sprint number, or milestone from argument
- Options: Skip
- Decision: Skip — findings are advisory
- Draft: Scope check report shown in conversation only
- Approval: Skip — read-only; no files written
Output
Deliver exactly:
- Scope delta: +X% items vs original plan (quantified, not subjective)
- Additions list: new items not in original plan, each tagged as discovered requirement or gold-plating
- Recommended cuts: specific items to remove to restore original scope (or "None needed")
- Verdict:
ON TRACK/MINOR CREEP/SIGNIFICANT CREEP/OUT OF CONTROL — RE-PLAN