agentsclimarketplace

Erp crm cutover protocol

Skill Raishin/vanguard-frontier-agentic/skills/cross-functional/erp-crm-cutover-protocol

Curated marketplace of AI skills, agents, and rules for cloud, zero-trust, and compliance-aware engineering - works with Claude Code, Codex, Cursor, Copilot, and more.

Install
npx -y skills add Raishin/vanguard-frontier-agentic --skill erp-crm-cutover-protocol

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 18 stars18 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

What its author says it does

Copied from the file, not written here

Use this skill when a Dynamics 365 ERP or CRM implementation is approaching go-live and must progress through mock migration, data reconciliation, cutover runbook execution, rollback testing, and the Success by Design go-live gate before production switchover. Orchestrates d365-data-migration-cutover-agent as primary, d365-success-by-design-governance-agent for SbD gate sign-off, and d365-security-sod-governance-agent for separation-of-duties validation. Gates include reconciliation sign-off, rollback readiness, and SbD go-live gate. Never makes the go/no-go decision autonomously; all production-impacting steps require human owner and Microsoft FastTrack confirmation where applicable.

SKILL.md

8.0 KB, as published. Nobody here has run it

ERP / CRM Cutover Protocol

Purpose

This skill defines the controlled sequence for taking a Dynamics 365 ERP or CRM implementation from pre-production readiness through mock migration, data reconciliation, runbook execution, rollback validation, and the Success by Design (SbD) go-live gate to production go-live. It exists so that no cutover proceeds without tested rollback paths, reconciled data, and explicit stakeholder sign-off at each gate. It does not execute migration scripts or production deployments; it structures the process so human owners can make well-informed go/no-go decisions.

When to use

  • A Dynamics 365 Finance, Supply Chain Management, Customer Engagement, or Business Central implementation is entering the Prepare phase and a cutover plan must be validated.
  • A mock cutover has been completed and reconciliation findings must be reviewed before the real cutover is authorised.
  • An organisation needs to confirm SbD go-live gate criteria before requesting Microsoft FastTrack go-live readiness review.
  • An existing production environment must be refreshed or migrated to a new release and cutover risk must be assessed.

When NOT to use

  • The go-live has already completed and this is post-go-live hypercare support — use the hypercare support runbook instead.
  • The migration involves a third-party ERP not on the Dynamics 365 platform — this protocol is scoped to Dynamics 365.
  • You need live production database or environment access to execute migration scripts — that requires the infrastructure owner; this protocol is recommendation-only.

Participating agents

  • d365-data-migration-cutover-agent (primary — mock migration, data reconciliation, cutover runbook, rollback plan)
  • d365-success-by-design-governance-agent (SbD gate review, go-live readiness sign-off)
  • d365-security-sod-governance-agent (separation of duties validation, security role sign-off)

Inputs required

  • Cutover plan document (task list, owners, timing, rollback steps)
  • Data migration strategy and scripts (for review, not execution)
  • Mock cutover results from sandbox environment (including error log)
  • Go-live checklist status from the SbD Prepare phase
  • Security role assignments and SoD analysis for go-live users
  • Integration test results and external dependency sign-off

Evidence required

  • At least one successful mock cutover has been completed in a sandbox environment that mirrors production
  • UAT has been completed and signed off by business stakeholders
  • Performance testing is complete and SLAs are met
  • Production environment is provisioned and matches the version in development/test environments
  • Rollback plan has been tested and timing confirmed

Workflow

  1. Mock cutover review — Review mock cutover results. Identify all errors, timing overruns, and unresolved issues. Confirm the mock was run with production-representative data and all integration steps.
  2. Data reconciliation — Validate that migrated data matches source records within agreed tolerance thresholds. Identify exceptions and require sign-off from the data owner on accepted variances.
  3. Gate 1 — Reconciliation sign-off — Data owner and project lead must formally sign off that reconciliation thresholds are met. d365-data-migration- cutover-agent produces the reconciliation report. Do not proceed without this sign-off.
  4. Rollback plan validation — Confirm the rollback plan is documented, tested, and timed. Confirm who has authority to invoke rollback and the criteria that trigger it.
  5. Gate 2 — Rollback tested — Confirm rollback has been rehearsed in the sandbox. d365-data-migration-cutover-agent attests rollback is feasible within the cutover window. Do not proceed without this confirmation.
  6. SoD validation — d365-security-sod-governance-agent reviews production security role assignments for separation-of-duties violations. Flag any violations for remediation before go-live.
  7. SbD go-live gate — d365-success-by-design-governance-agent runs the SbD go-live readiness review against the full go-live checklist: solution scope, UAT sign-off, performance, integrations, data migration, change management, support readiness. Produce a go/conditional-go/no-go recommendation.
  8. Gate 3 — SbD go-live gate sign-off — Project steering committee and Microsoft FastTrack (where applicable) must confirm the go-live gate. This protocol never issues the final go/no-go autonomously.
  9. Cutover execution readiness — Confirm all people, environments, and communication plans are in place. Verify the cutover window is realistic given mock timing plus buffer.
  10. Post-cutover validation — After go-live, confirm data accuracy in production, integration health, and user access. Invoke hypercare plan.

Decision gates

GateConditionAction
Reconciliation sign-offData variances exceed agreed thresholdsStop cutover; require data owner resolution
Rollback testedRollback not rehearsed or timing exceeds windowStop cutover; require rollback rehearsal
SoD violationsProduction roles contain SoD conflictsEscalate to d365-security-sod-governance-agent; remediate before go-live
SbD go-live gateAny SbD blocking issues unresolvedStop cutover; require issue owner sign-off
Mock cutover errorsCritical errors unresolved from mockStop cutover; require second mock

Refusal triggers

  • Stop if no successful mock cutover has been completed — do not recommend production go-live without at least one successful rehearsal.
  • Stop if reconciliation sign-off has not been obtained from the data owner.
  • Stop if the rollback plan is untested or the rollback window exceeds what the business can tolerate.
  • Stop if SbD blocking issues are unresolved — do not substitute judgement for the SbD gate process.
  • Stop if credentials, production org IDs, or customer data are requested as inputs to this protocol — refuse and escalate.

Handoff rules

  • All handoffs carry: project_id, skill_id, skill_version, invoked_by, gate_status, open_issues, rollback_status, sbd_verdict, do_not_do_list.
  • Human go/no-go decisions are always documented with decision-maker name, date, and statement of accepted risk.
  • SbD gate sign-off from d365-success-by-design-governance-agent is the minimum required before any production cutover recommendation.

KPIs

  • Mock cutover success rate (errors per rehearsal)
  • Data reconciliation pass rate (% within tolerance)
  • Rollback rehearsal completion (yes/no with timing)
  • SbD go-live gate outcome (go / conditional-go / no-go)
  • Actual vs. planned cutover window duration

References

Keep looking

Skills are one crate of 328,083. Ordering is by how many stacks a row turns up in, so the top of any crate is what has actually been picked rather than what has the most stars.