Erp crm cutover protocol

Skill Raishin/vanguard-frontier-agentic/skills/cross-functional/erp-crm-cutover-protocol

Use this skill when a Dynamics 365 ERP or CRM implementation is approaching go-live and must progress through mock migration, data reconciliation, cutover runbook execution, rollback testing, and the Success by Design go-live gate before production switchover. Orchestrates d365-data-migration-cutover-agent as primary, d365-success-by-design-governance-agent for SbD gate sign-off, and d365-security-sod-governance-agent for separation-of-duties validation. Gates include reconciliation sign-off, rollback readiness, and SbD go-live gate. Never makes the go/no-go decision autonomously; all production-impacting steps require human owner and Microsoft FastTrack confirmation where applicable.From its SKILL.md

Install
npx -y skills add Raishin/vanguard-frontier-agentic --skill erp-crm-cutover-protocol

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 20 stars20 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

SKILL.md

8.0 KB, ~1.6k tokens by cl100k_base, as published. Nobody here has run it

ERP / CRM Cutover Protocol

Purpose

This skill defines the controlled sequence for taking a Dynamics 365 ERP or CRM implementation from pre-production readiness through mock migration, data reconciliation, runbook execution, rollback validation, and the Success by Design (SbD) go-live gate to production go-live. It exists so that no cutover proceeds without tested rollback paths, reconciled data, and explicit stakeholder sign-off at each gate. It does not execute migration scripts or production deployments; it structures the process so human owners can make well-informed go/no-go decisions.

When to use

  • A Dynamics 365 Finance, Supply Chain Management, Customer Engagement, or Business Central implementation is entering the Prepare phase and a cutover plan must be validated.
  • A mock cutover has been completed and reconciliation findings must be reviewed before the real cutover is authorised.
  • An organisation needs to confirm SbD go-live gate criteria before requesting Microsoft FastTrack go-live readiness review.
  • An existing production environment must be refreshed or migrated to a new release and cutover risk must be assessed.

When NOT to use

  • The go-live has already completed and this is post-go-live hypercare support — use the hypercare support runbook instead.
  • The migration involves a third-party ERP not on the Dynamics 365 platform — this protocol is scoped to Dynamics 365.
  • You need live production database or environment access to execute migration scripts — that requires the infrastructure owner; this protocol is recommendation-only.

Participating agents

  • d365-data-migration-cutover-agent (primary — mock migration, data reconciliation, cutover runbook, rollback plan)
  • d365-success-by-design-governance-agent (SbD gate review, go-live readiness sign-off)
  • d365-security-sod-governance-agent (separation of duties validation, security role sign-off)

Inputs required

  • Cutover plan document (task list, owners, timing, rollback steps)
  • Data migration strategy and scripts (for review, not execution)
  • Mock cutover results from sandbox environment (including error log)
  • Go-live checklist status from the SbD Prepare phase
  • Security role assignments and SoD analysis for go-live users
  • Integration test results and external dependency sign-off

Evidence required

  • At least one successful mock cutover has been completed in a sandbox environment that mirrors production
  • UAT has been completed and signed off by business stakeholders
  • Performance testing is complete and SLAs are met
  • Production environment is provisioned and matches the version in development/test environments
  • Rollback plan has been tested and timing confirmed

Workflow

  1. Mock cutover review — Review mock cutover results. Identify all errors, timing overruns, and unresolved issues. Confirm the mock was run with production-representative data and all integration steps.
  2. Data reconciliation — Validate that migrated data matches source records within agreed tolerance thresholds. Identify exceptions and require sign-off from the data owner on accepted variances.
  3. Gate 1 — Reconciliation sign-off — Data owner and project lead must formally sign off that reconciliation thresholds are met. d365-data-migration- cutover-agent produces the reconciliation report. Do not proceed without this sign-off.
  4. Rollback plan validation — Confirm the rollback plan is documented, tested, and timed. Confirm who has authority to invoke rollback and the criteria that trigger it.
  5. Gate 2 — Rollback tested — Confirm rollback has been rehearsed in the sandbox. d365-data-migration-cutover-agent attests rollback is feasible within the cutover window. Do not proceed without this confirmation.
  6. SoD validation — d365-security-sod-governance-agent reviews production security role assignments for separation-of-duties violations. Flag any violations for remediation before go-live.
  7. SbD go-live gate — d365-success-by-design-governance-agent runs the SbD go-live readiness review against the full go-live checklist: solution scope, UAT sign-off, performance, integrations, data migration, change management, support readiness. Produce a go/conditional-go/no-go recommendation.
  8. Gate 3 — SbD go-live gate sign-off — Project steering committee and Microsoft FastTrack (where applicable) must confirm the go-live gate. This protocol never issues the final go/no-go autonomously.
  9. Cutover execution readiness — Confirm all people, environments, and communication plans are in place. Verify the cutover window is realistic given mock timing plus buffer.
  10. Post-cutover validation — After go-live, confirm data accuracy in production, integration health, and user access. Invoke hypercare plan.

Decision gates

GateConditionAction
Reconciliation sign-offData variances exceed agreed thresholdsStop cutover; require data owner resolution
Rollback testedRollback not rehearsed or timing exceeds windowStop cutover; require rollback rehearsal
SoD violationsProduction roles contain SoD conflictsEscalate to d365-security-sod-governance-agent; remediate before go-live
SbD go-live gateAny SbD blocking issues unresolvedStop cutover; require issue owner sign-off
Mock cutover errorsCritical errors unresolved from mockStop cutover; require second mock

Refusal triggers

  • Stop if no successful mock cutover has been completed — do not recommend production go-live without at least one successful rehearsal.
  • Stop if reconciliation sign-off has not been obtained from the data owner.
  • Stop if the rollback plan is untested or the rollback window exceeds what the business can tolerate.
  • Stop if SbD blocking issues are unresolved — do not substitute judgement for the SbD gate process.
  • Stop if credentials, production org IDs, or customer data are requested as inputs to this protocol — refuse and escalate.

Handoff rules

  • All handoffs carry: project_id, skill_id, skill_version, invoked_by, gate_status, open_issues, rollback_status, sbd_verdict, do_not_do_list.
  • Human go/no-go decisions are always documented with decision-maker name, date, and statement of accepted risk.
  • SbD gate sign-off from d365-success-by-design-governance-agent is the minimum required before any production cutover recommendation.

KPIs

  • Mock cutover success rate (errors per rehearsal)
  • Data reconciliation pass rate (% within tolerance)
  • Rollback rehearsal completion (yes/no with timing)
  • SbD go-live gate outcome (go / conditional-go / no-go)
  • Actual vs. planned cutover window duration