Ultimate plan-and-execute skill v2. 13 stages: Check, Research, Dependency Analysis, Plan Draft, Estimation & Risk, Critical Review, Quality Score, Approval & Decision Register, GitHub Sync, What-If Simulation, Execute, Auto Re-Plan, Verify, Post-Mortem & Learn. Adds: Plan JSON Schema, Dependency DAG, 3-Point Estimation (PERT), Monte Carlo, Risk Scoring (0-100), OKR Framework, Decision Register, Assumptions Log, Plan Quality Score (0-100), Auto Re-Plan Triggers, Plan Templates, Multi-Stage Approval, What-If Simulation, Post-Mortem Learning Loop, Blocker Detection, Plan Versioning, Continuous Planning Mode. Replaces /check-plan-done, /omoc-plan-swarm, /biometrics-plan.From its SKILL.md

Install
npx -y skills add OpenSIN-AI/OpenSIN-Skills --skill plan

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

2 things to look at

  • no licenseNo license file was found in the repository. Code published without one is not open source by default, so using it at work is a question for whoever answers licensing questions where you are.
  • 2 stars2 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

What its file declares

Copied from the file, not written here

The file declares its own license as MIT. That is the author’s claim about this one file, and it is not the same thing as the license GitHub reports for the repository, which is listed with the other numbers below.

SKILL.md

26.2 KB, ~6.7k tokens by cl100k_base, as published. Nobody here has run it

/plan v2 - World-Class Plan & Execute Skill

Check, Research, Analyze, Plan, Score, Review, Approve, Sync, Simulate, Execute, Verify, Learn

Replaces: /check-plan-done, /omoc-plan-swarm, /biometrics-plan Version: 2.0 - World-Class Planning Features Integrated


Purpose

One skill for everything planning-related. Modes:

  • plan-only: Strategy, roadmap, architecture only
  • plan-and-execute: Build, fix, implement, ship
  • resume-approved-plan: Continue existing approved plan
  • continuous-planning: Living plan with auto-adaptation

Incorporates best practices from Linear (Visual Initiatives), GitHub Projects (Code-Adjacent Roadmaps), Amazon Working Backwards (PR/FAQ), Netflix (Outcome-Driven), Stripe OKRs (Narrative 6-Pagers), GitLab Epics (Radical Transparency), Shopify (Async Anti-OKR), Notion (Database-Driven), Jira Advanced Roadmaps (Enterprise Portfolio).


Trigger Words

plan, plane, planung, planning, erstelle einen plan, create a plan, roadmap, strategy, strategie, konzept, blueprint, architektur


Design Principles

  1. Pipeline over Hierarchy - sequential stages with clear I/O contracts
  2. Outcome over Output - plans measured by business/user outcomes (OKRs), not task completion
  3. Data-Driven Estimation - 3-point estimates with PERT formula, not gut feelings
  4. Dependency-Aware - explicit DAG for critical path identification
  5. Quantified Risk - numerical risk scores (0-100) with expected value
  6. Fail-Fast Gates - check quality BEFORE passing to next stage
  7. Parallel Where Independent - research runs parallel, rest sequential
  8. No Fictional Agents - real OpenCode tools only
  9. Cost Guardrails - bounded calls, no unbounded loops
  10. GitHub is Truth - approved plans synced to GitHub Issues
  11. Continuous over Batch - plans are living documents
  12. Decision Velocity - how fast can we pivot on new data
  13. Learn from History - every plan feeds accuracy back

Modes

ModeWhenFlow
plan-onlyStrategy, roadmap, architectureStages 0 through 3.5, then stop
plan-and-executeBuild, fix, implement, shipFull Stages 0 through 7
resume-approved-planExisting approved plan matchesSkip to Stage 5 (Execute)
continuous-planningLiving plan with auto-adaptationFull loop with monitor and auto-re-plan

Core Rules

  • Real OpenCode tools only
  • Bounded research: 2 parallel, 1 synthesis, 1 review
  • Short single-purpose prompts
  • Session context by default
  • No fictional agents or undefined file dependencies
  • No auto-commit in core loop
  • Derive validation from actual stack
  • Max 1 revision after critical review
  • Continue until done criteria pass or real blocker
  • KING CEO TRACKING: Git repo = sync to GitHub Issues before execution
  • OUTCOME FIRST: Every plan defines measurable OKRs
  • DEPENDENCY DAG: Every plan models task dependencies as DAG
  • RISK SCORE: Every plan has quantified overall risk (0-100)
  • QUALITY SCORE: Every plan must pass minimum 70/100
  • PLAN VERSIONING: Every change creates new version with diff

Architecture

STAGE 0:    CHECK - Existing approved plan?
STAGE 1:    RESEARCH (parallel) - Librarian + Explore
STAGE 1.5:  DEPENDENCY ANALYSIS - Build DAG, find critical path
STAGE 2:    PLAN DRAFT - Synthesize with OKRs, phases, tasks, deps, risks
STAGE 2.5:  ESTIMATION & RISK - PERT, Monte Carlo, risk scoring, rollback
STAGE 3:    CRITICAL REVIEW - Hard review by artistry agent
STAGE 3.2:  QUALITY SCORE - Auto-calculate 0-100
STAGE 3.5:  APPROVAL & DECISION REGISTER - Multi-stage, decision log, assumptions
STAGE 4:    SYNC - GitHub Project/Issue creation
STAGE 4.5:  WHAT-IF SIMULATION - Delay, resource, risk scenarios
STAGE 5:    EXECUTE - Task-by-task with validation
STAGE 5.5:  AUTO RE-PLAN - Triggered by slip, blocker, scope change
STAGE 6:    VERIFY - All done criteria + outcome measurement
STAGE 6.5:  POST-MORTEM & LEARNING - Accuracy metrics, retrospective, velocity update
STAGE 7:    CLOSEOUT - GitHub close, Wiki sync

Plan JSON Schema v2

Every plan MUST conform to this schema:

{
  "$schema": "https://opencode.ai/schemas/plan-v2.json",
  "version": "2.0.0",
  "id": "plan_YYYY-MM-DD_NNN",
  "title": "Plan Title",
  "mode": "plan-only|plan-and-execute|resume-approved-plan|continuous-planning",
  "created": "YYYY-MM-DD",
  "updated": "YYYY-MM-DD",
  "version_number": 1,
  "status": "draft|approved|in-progress|completed|re-planned",

  "outcomes": {
    "objective": "What business/user outcome",
    "key_results": [
      {"metric": "metric name", "target": "target value", "current": "current value"}
    ]
  },

  "current_state": {
    "strengths": ["list"],
    "weaknesses": ["list"],
    "critical_gaps": ["list"]
  },

  "decisions": [
    {"decision": "what", "rationale": "why", "alternatives": ["list"], "owner": "role", "date": "YYYY-MM-DD"}
  ],

  "assumptions": [
    {"assumption": "what", "confidence": 0.95, "validation": "how to check"}
  ],

  "phases": [
    {
      "id": "P1",
      "name": "Phase Name",
      "priority": "critical|high|medium|optional",
      "tasks": [
        {
          "id": "P1-T1",
          "description": "What to do",
          "effort": {"pessimistic": "4h", "realistic": "2h", "optimistic": "1h"},
          "dependencies": ["P1-T0"],
          "validation": "How to verify",
          "owner": "role",
          "status": "not-started|in-progress|done|blocked"
        }
      ]
    }
  ],

  "dependency_graph": {
    "nodes": ["P1-T1", "P1-T2"],
    "edges": [{"from": "P1-T1", "to": "P1-T2", "type": "hard|soft|external"}],
    "critical_path": ["P1-T1", "P1-T2"]
  },

  "risks": [
    {
      "id": "R1",
      "description": "What could go wrong",
      "likelihood": 0.3,
      "impact": 8,
      "score": 24,
      "mitigation": "What to do about it",
      "owner": "role",
      "status": "identified|mitigated|occurred"
    }
  ],

  "overall_risk_score": 24,
  "plan_quality_score": 85,

  "rollback_plan": {
    "trigger": "What triggers rollback",
    "action": "What to do",
    "max_loss": "Worst case"
  },

  "done_criteria": [
    {"criterion": "Measurable outcome", "status": "not-met|met"}
  ],

  "approvals": [
    {"role": "tech-lead", "status": "pending|approved|rejected", "date": null}
  ],

  "metrics": {
    "planned_duration_hours": 40,
    "confidence_50": "35h",
    "confidence_85": "52h",
    "confidence_95": "68h",
    "scope_creep_count": 0,
    "replan_count": 0
  },

  "learning": {
    "planned_vs_actual": null,
    "accuracy_score": null,
    "retrospective": null
  }
}

Stage 0: Check

Before planning, answer:

  1. Is there already an approved plan in current session or task context?
  2. Does that plan still match the current request?
  3. Does it contain: outcomes (OKRs), concrete tasks, dependency DAG, risk scores, validation steps, done criteria?
  4. Has the plan been synced to GitHub Issues?

If YES to all four, skip to Stage 5 in resume-approved-plan mode. Otherwise, create fresh plan starting at Stage 1.


Stage 1: Research (parallel)

Run both tasks in parallel with run_in_background: true.

Task A: Librarian - Web and Docs Research

task({
  subagent_type: "librarian",
  run_in_background: true,
  load_skills: [],
  description: "Best-practice research for: [TOPIC]",
  prompt: `
Research this implementation topic. Focus on 2025-2026 sources.

TOPIC: [insert task description]
DATE: [today's date]

Deliver:
1. Current best practices with source URLs
2. Stable production-ready technology versions
3. Known anti-patterns to avoid
4. Community consensus from experts
5. Real-world case studies from top companies (Amazon, Linear, Stripe, GitHub, Netflix)
6. Tool recommendations with pros and cons

Output: concise markdown with concrete findings and sources.
No filler. Only verified, current information.
  `
})

Task B: Explore - Codebase Analysis

task({
  subagent_type: "explore",
  run_in_background: true,
  load_skills: [],
  description: "Context analysis for: [TOPIC]",
  prompt: `
Analyze the local codebase or project context.

TASK: [insert task description]
PATH: [project path]

Deliver:
1. Project structure and tech stack (versions from lock files)
2. Existing patterns to preserve, code quality assessment
3. Dependencies: outdated, vulnerable, or unused
4. Integration points that could break during changes
5. Gaps: what is missing for production-readiness
6. Validation commands already used by the project
7. Implicit dependencies between services or modules
8. Circular dependency analysis if applicable

Output: concise markdown with file:line references.
  `
})

Gate 1: Research Quality

Do not proceed unless:

  • Librarian returned concrete findings with source URLs
  • Explore returned file references and specific findings
  • Both outputs contain 200+ words of substance
  • Research identifies both good patterns AND failure risks
  • Dependency analysis covers service, data, and team dependencies

If one branch is weak, re-run only that branch once with tighter prompt. If both are weak, stop and report.


Stage 1.5: Dependency Analysis

Build a Dependency DAG from research outputs:

  1. Extract explicit and implicit dependencies from research
  2. Classify: hard (blocking), soft (nice-to-have), external (third-party)
  3. Map critical path: longest path through dependency graph
  4. Identify blockers: tasks with no parallel execution path
  5. Single points of failure: tasks blocking multiple downstream items
  6. External dependencies: APIs, services, teams outside your control

Output: Mermaid diagram and JSON dependency graph in the plan.


Stage 2: Draft Plan (sequential)

Synthesize one execution-ready plan from research outputs.

task({
  category: "deep",
  load_skills: [],
  run_in_background: false,
  description: "Create plan for: [TOPIC]",
  prompt: `
Create an execution-ready plan following Plan JSON Schema v2.

TASK: [insert task description]
BEST PRACTICES: [paste Librarian output]
LOCAL CONTEXT: [paste Explore output]

Use this EXACT structure:

# Plan: [Title]
Mode: [plan-only | plan-and-execute | resume-approved-plan | continuous-planning]
Created: [date] | Scope: [what] | Version: 1

## Outcomes (OKRs)
**Objective:** [what business or user outcome]
**Key Results:**
- KR1: [metric] from [current] to [target]
- KR2: [metric] from [current] to [target]

## Current State
[strengths, weaknesses, critical gaps]

## Decisions
| Decision | Rationale | Alternatives | Owner |
|----------|-----------|-------------|-------|

## Assumptions
| Assumption | Confidence | Validation Method |
|------------|-----------|-------------------|

## Phases

### Phase 1: [name] - CRITICAL
- [ ] P1-T1: [task] (P=4h/R=2h/O=1h, deps: [], validation: ...)
- [ ] P1-T2: [task] (P=/R=/O=, deps: [P1-T1], validation: ...)

### Phase 2: [name] - HIGH
- [ ] P2-T1: [task] (P=/R=/O=, deps: [P1-T2], validation: ...)

### Phase 3: [name] - OPTIONAL
- [ ] P3-T1: [task] (P=/R=/O=, deps: [P2-T1], validation: ...)

## Dependency Graph
[Mermaid diagram or text description]
Critical Path: P1-T1 -> P1-T2 -> P2-T1

## Risk Register
| ID | Risk | Likelihood (0-1) | Impact (1-10) | Score | Mitigation | Owner |
|----|------|-----------------|---------------|-------|------------|-------|
Overall Risk Score: [0-100]

## Rollback Plan
- Trigger: [what triggers rollback]
- Action: [what exactly to do]
- Max Loss: [worst-case time or data loss]

## Done Criteria
- [ ] [measurable outcome tied to OKR]
- [ ] [validation passes]
- [ ] [no regressions]

## Approval Gates
- [ ] Tech Lead
- [ ] Engineering Manager
- [ ] Product Owner (if user-facing)

RULES:
- Every task must be concrete and actionable
- Every task must include: 3-point estimate, dependencies, validation
- Effort estimates mandatory: Pessimistic, Realistic, Optimistic
- Phase 1 must be smallest critical path
- Maximum 3 phases
- Every risk needs likelihood (0-1), impact (1-10), score = likelihood times impact
- Overall risk score = sum of all risk scores, capped at 100
  `
})

Gate 2: Plan Completeness

Do not proceed unless the plan includes:

  • Outcomes or OKRs section with measurable key results
  • Current state analysis
  • Decisions table with rationale
  • Assumptions table with confidence levels
  • At least one phase with concrete tasks
  • 3-point estimates (P/R/O) on every task
  • Explicit dependencies per task
  • Validation step per task
  • Dependency graph
  • Risk register with scores
  • Overall risk score (0-100)
  • Rollback plan
  • Done criteria
  • Approval gates

If sections are missing, fix the plan before review.


Stage 2.5: Estimation and Risk Analysis

3-Point Estimation (PERT Formula)

For each task:

  • Pessimistic (P): everything goes wrong
  • Realistic (R): normal conditions
  • Optimistic (O): everything goes right
  • Expected (E) = (P + 4*R + O) / 6

Monte Carlo Simulation (simplified)

total_pessimistic = sum(all P estimates)
total_realistic = sum(all R estimates)
total_optimistic = sum(all O estimates)
expected_total = (total_pessimistic + 4*total_realistic + total_optimistic) / 6
std_dev = (total_pessimistic - total_optimistic) / 6

confidence_50 = expected_total
confidence_85 = expected_total + std_dev
confidence_95 = expected_total + 2*std_dev

Risk Scoring

risk_score = likelihood (0.0-1.0) times impact (1-10)
overall_risk = min(100, sum(all risk_scores))

Risk level:
0-20:   LOW - proceed with monitoring
21-40:  MEDIUM - proceed with mitigation
41-60:  HIGH - proceed only with approved mitigations
61-80:  CRITICAL - re-scope or add resources
81-100: BLOCKER - cannot proceed, must re-plan

Gate 2b: Estimation Confidence

Do not proceed unless:

  • All tasks have 3-point estimates
  • Confidence 95th percentile is within 2x of expected total
  • Overall risk score is 60 or below

Stage 3: Critical Review (sequential)

One hard review. Be direct. No praise.

task({
  category: "artistry",
  load_skills: [],
  run_in_background: false,
  description: "Critical review of plan for: [TOPIC]",
  prompt: `
Review this plan critically. Be direct. No praise.

PLAN:
[paste plan from Stage 2]

Checklist:
1. OUTCOME ALIGNMENT - Do tasks directly achieve OKRs?
2. CRITICAL GAPS - What is missing that would cause failure?
3. FALSE ASSUMPTIONS - What does the plan assume without proof?
4. DEPENDENCY ERRORS - Are deps correct? Is critical path right?
5. ESTIMATION QUALITY - Are estimates realistic?
6. RISK COVERAGE - Are major risks identified? Scores realistic?
7. PRIORITY ERRORS - Is Phase 1 actually the critical path?
8. SCOPE - Realistic or overambitious?
9. TECH CHOICES - Sound for 2026?
10. NEW DEBT - Does this CREATE technical debt?
11. ROLLBACK ADEQUACY - If Phase 1 fails, is rollback sufficient?

Output format:

## Verdict: APPROVED or NEEDS REVISION

## Issues by severity
### CRITICAL
- ...
### HIGH
- ...
### LOW
- ...

## Suggested Changes
[Concrete rewrites, not vague advice]

RULES:
- If solid, say APPROVED with only minor improvements
- If CRITICAL issues, say NEEDS REVISION and be specific
- Never say "looks good overall"
  `
})

Gate 3: Approval Readiness

VerdictAction
APPROVED, no CRITICALContinue to Stage 3.2
NEEDS REVISION with CRITICALIntegrate changes yourself, re-check, max 1 revision
Still critical after 1 revisionStop, present with OPEN ISSUES

Stage 3.2: Plan Quality Score

Auto-calculate quality score (0-100):

CategoryWeightCriteria
Completeness25All sections present, OKRs defined, deps mapped
Clarity20Tasks unambiguous, validation clear, criteria measurable
Risk Coverage20Major risks identified, scores realistic, mitigations defined
Estimation Quality153-point estimates present, confidence intervals reasonable
Dependency Modeling10DAG correct, critical path identified, blockers flagged
Outcome Alignment10Every task maps to KR, OKRs measurable

Quality Score formula: (completeness divided by 100 times 25) + (clarity divided by 100 times 20) + (risk_coverage divided by 100 times 20) + (estimation_quality divided by 100 times 15) + (dependency_modeling divided by 100 times 10) + (outcome_alignment divided by 100 times 10)

Gate 3b: Quality Threshold

  • 85+: Excellent, proceed immediately
  • 70-84: Good, proceed with noted improvements
  • 50-69: Needs work, fix before review
  • Below 50: Unacceptable, re-plan from scratch

Stage 3.5: Multi-Stage Approval and Decision Register

Approval Workflow

Tech Lead, then Engineering Manager, then Product Owner if user-facing.

gh issue create --title "[Approval] [Role] - Plan: <title>" \
  --body "<plan summary>" \
  --label "approval,plan:<title>" \
  --assignee <role-owner>

Decision Register

DecisionRationaleAlternativesDecided ByDateStatus

Assumptions Log

AssumptionConfidenceValidationStatus

If plan-only mode, return approved plan and stop. If plan-and-execute mode, continue to Stage 4.


Stage 4: Sync - GitHub Project and Issue Creation

Option A: Issue Architect (Recommended)

node ~/dev/sin-solver-control-plane/packages/cli/src/index.mjs issues \
  --plan <path_to_plan.md> \
  --repo <owner/repo> \
  --phase <phase_id> \
  --dry-run

Remove --dry-run for real creation.

Option B: Manual GitHub (Fallback)

gh issue create --title "[Master] <plan title>" \
  --body "<plan markdown>" --label "master-tracker,plan"

Option C: Linear or Jira or Asana (if configured)

# Linear
linear-cli issue create --title "<title>" --label "plan" --estimate <points>

# Jira
jira create --project <key> --issuetype Epic --summary "<title>"

Output the created tracker URL.


Stage 4.5: What-If Simulation

Run 2-3 scenarios before execution:

task({
  category: "deep",
  load_skills: [],
  run_in_background: false,
  description: "What-if simulation for plan",
  prompt: `
Simulate these scenarios:

PLAN: [paste plan]

SCENARIOS:
1. DELAY: What if critical path task takes 2x longer?
2. RESOURCE: What if we add one more developer?
3. RISK: What if Risk R1 materializes?

For each: new completion date, affected tasks, recommended mitigation, whether re-planning is needed.

Output: scenario analysis table with pass or fail verdict.
  `
})

Stage 5: Execute

Turn approved plan into live task loop.

Execution rules:

  • One concrete task at a time
  • Keep aligned with approved phase order
  • Run exact validation after each task
  • Mark done ONLY after validation passes
  • Live Tracker Update: gh issue comment <ID> --body "Done: <details>"
  • Burndown Tracking: update remaining effort after each task
  • Fix validation failures before moving on
  • One focused background consultation if truly blocked
  • Do NOT claim success while done criteria are open
  • No unbounded orchestration loop

Stage 5.5: Automated Re-Plan Triggers

TriggerThresholdAction
Schedule SlipActual over 120% of plannedRe-estimate remaining
Blocker DetectedTask blocked over 24hRe-scope or escalate
Scope CreepMore than 2 new requirementsRe-plan with new scope
Risk MaterializedAny risk status = occurredActivate mitigation, re-plan if needed
Resource ChangeTeam size changesRe-estimate with new capacity
Dependency FailureExternal dependency unavailableFind alternative or re-plan

When re-plan triggered:

  1. Log re-plan event with reason
  2. Jump to Stage 2
  3. Keep previous learnings and decisions
  4. Increment plan version number
  5. Re-run review (Stage 3) and quality score (Stage 3.2)

Stage 6: Verify Done

Before stopping:

  • Every required task completed or explicitly deferred with reason
  • Every done criterion passes
  • All critical validations passed
  • Remaining risks or open issues stated clearly
  • Tracker Closeout: close GitHub sub-tasks and master epic with final summary
  • Outcome Verification: Key Results measured and compared to targets

Return:

  • What was completed
  • What was validated
  • What remains open
  • Plan accuracy metrics (planned vs actual)

If work is not done, continue the loop.


Stage 6.5: Post-Mortem and Learning Loop

Plan Accuracy Metrics

accuracy_score = 1 - |actual_duration - planned_duration| / planned_duration
per_task_accuracy = average(1 - |actual_i - planned_i| / planned_i for each task i)
scope_creep_rate = new_tasks_added / original_task_count
replan_rate = replan_count / total_plans

Retrospective Template

gh issue comment <MASTER_ID> --body "
## Retrospective

### What Went Well
- [items]

### What Could Be Better
- [items]

### Plan Accuracy
- Planned: X hours, Actual: Y hours, Accuracy: Z%
- Tasks on time: N/M
- Scope changes: K
- Re-plans: R

### Learnings for Future Plans
- [specific insight]
- [estimation adjustment]
- [process improvement]
"

Velocity Baseline Update

Store actual durations for future estimation:

velocity_db[task_type] = {
  avg_duration: ...,
  std_dev: ...,
  sample_count: ...,
  last_updated: ...
}

Stage 7: Closeout

Issue Board Closeout

gh issue close <ID> --comment "Completed: <summary>"

gh issue close <EPIC_ID> --comment "
## Final Status
Completed: X/Y tasks
Validated: <results>
Plan Accuracy: Z%
Open issues: <none or list>
"

Wiki Documentation Sync

If the project has a GitHub Wiki:

  1. Run ~/.config/opencode/scripts/sync-github-wiki.sh <plan_path>
  2. If script reports "WIKI NOT INITIALIZED", use browser automation to create initial page, then re-run.

Anti-Patterns To Reject

Anti-PatternWhyReplacement
Vague quality claimsNot measurableConcrete gates with pass/fail
Hidden dependenciesBrittleExplicit dependency DAG
Story pointsAbstract, gameablePERT 3-point estimation with historical data
Static risk matrixOutdated instantlyReal-time RAG from CI/CD health, bugs, scope creep
Annual batch planningToo slow for 2026Continuous planning with decision velocity
Planning without outcomesTasks for tasks sakeOKR-first, outcome-driven planning
Fictional agent namesNo real tool mappingReal task() with subagent_type or category
Mandatory auto-commitUnsafe, destructiveExplicit commit only when user requests
Planning without reviewBlind spotsStage 3 critical review mandatory
Execution without done criteriaCannot verifyEvery plan MUST have done criteria
Infinite loopsResource wasteBounded loops with stop conditions
Premature successUser loses trustVerify ALL done criteria before stopping
Plans without rollbackNo safety netEvery plan needs rollback trigger and action
Plans without versioningCannot track changesEvery change increments version with diff
Subjective project healthPM gut feelingAlgorithmic RAG from pipeline, bugs, scope
Output metrics over outcomesRevenue targets miss qualityControllable Input Metrics (Amazon style)

Cost Awareness

StageCallsLatencyNotes
Research2 parallel1 LLM roundLibrarian + Explore simultaneously
Plan Draft1 sequential1 LLM roundSynthesizes research
Review1 sequential1 LLM roundCritical review
Simulation0-1 sequential0-1 LLM roundsOptional what-if
Total Planning4-5 calls4-5 LLM roundsvs 6+ in old designs
  • Re-run only weak research branch, not both
  • Max 1 revision round after review
  • Results stay in session context, no temp files

Tool Reference

StageToolPurpose
Researchtask(subagent_type: librarian)Web and docs research
Researchtask(subagent_type: explore)Codebase analysis
Plantask(category: deep)Synthesize plan
Reviewtask(category: artistry)Critical review
Simulationtask(category: deep)What-if scenarios
Syncgh issue create or Issue Architect CLIPersist to GitHub
Executegh issue commentLive tracker updates
Closeoutgh issue closeIssue board closeout

Plan Templates

Use these templates for common scenarios. Load the template, fill in specifics.

Feature Build Template

  • Phase 1: API and data model (critical path)
  • Phase 2: UI and integration
  • Phase 3: Polish and edge cases (optional)

Bug Fix Template

  • Phase 1: Reproduce and root cause (critical)
  • Phase 2: Fix and regression tests
  • Phase 3: Monitor in production (optional)

Migration Template

  • Phase 1: Build parallel system (critical)
  • Phase 2: Dual-write and verify
  • Phase 3: Cutover and cleanup

Refactor Template

  • Phase 1: Add tests around current behavior (critical)
  • Phase 2: Incremental refactoring
  • Phase 3: Remove old code

Practical Summary

  1. Check whether usable approved plan exists
  2. Research with bounded parallel tasks (Librarian + Explore)
  3. Analyze dependencies and build DAG
  4. Plan with OKRs, 3-point estimates, risk scoring
  5. Score quality (minimum 70/100)
  6. Review with hard critique gate
  7. Approve with decision register
  8. Sync to GitHub Issues
  9. Simulate what-if scenarios
  10. Execute task by task with validation
  11. Auto-re-plan on slip, blocker, scope change
  12. Verify all done criteria and measure outcomes
  13. Post-mortem: accuracy metrics, retrospective, velocity update
  14. Closeout: GitHub close, Wiki sync

That is what /plan v2 means. World-class planning. One skill.