Estimation

Skill meaningfy-ws/skillery/skills/estimation

A lightweight fixed-cost scoping / estimation discipline that de-risks fixed-cost bids — a CHECKLIST + METHOD, not a heavy model. Produces a work breakdown plus PERT-weighted effort estimates, uncertainty ranges, assumptions & exclusions, and contingency, feeding the SoW scope boundary. PERT (three-point: optimistic / most-likely / pessimistic) is the default technique; analogous, parametric, and bottom-up are alternatives. Gantt charts / scheduling are rendered in EXTERNAL tools (Smartsheet, MS Project) from the work breakdown — this skill produces the breakdown + estimates, not the chart. It OWNS the estimation/scoping discipline; it DELEGATES the proposal/SoW wrapper to `proposal-writing`, the build breakdown to `epic-planning`, and sequencing to `decision-package`. Triggers — "estimate this engagement", "PERT estimate", "fixed-cost scoping", "work breakdown for estimation", "contingency / uncertainty range". Independently triggerable; also the pricing step of the `proposal-writing` flow.From its SKILL.md

Install
npx -y skills add meaningfy-ws/skillery --skill estimation

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 2 stars2 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

What its file declares

Copied from the file, not written here

The file declares its own license as Apache 2.0. That is the author’s claim about this one file, and it is not the same thing as the license GitHub reports for the repository, which is listed with the other numbers below.

SKILL.md

7.2 KB, as published. Nobody here has run it

Estimation

Provisional pending the first-engagement gate. This wiring is the floor, not the finished standard; refine it after the first real paid engagement is estimated and delivered against.

Overview

A fixed-cost scoping / estimation discipline that de-risks fixed-cost bids. It is deliberately light — a checklist plus a method, not a model. The job is to turn an engagement into a defensible number: a work breakdown, PERT-weighted effort with uncertainty ranges, explicit assumptions & exclusions, and contingency — then hand those to the SoW so the price and the scope boundary rest on the same evidence.

It is independently triggerable (any "estimate this" / "PERT estimate" request) and is also the pricing step of the proposal-writing flow.

It composes by reference: the estimate decomposes against the build breakdown owned by epic-planning, and its sequencing/roadmap framing comes from decision-package. It restates neither.

What it covers (R4)

  1. Decomposition (work breakdown). Break the engagement into estimable leaf items — small enough that each can carry a three-point estimate. For build-tier work, decompose against the EPIC/PLAN breakdown from epic-planning; do not invent a parallel breakdown.
  2. Uncertainty ranges. Each leaf gets a range, not a point. PERT (below) is how the range becomes a weighted estimate plus a variance you can roll up.
  3. Assumptions & exclusions. State what the number assumes (inputs, access, decisions, availability) and what it explicitly excludes. The exclusions are the SoW out-of-scope list — one list, two documents (see proposal-writing).
  4. Contingency. A buffer sized from the rolled-up variance and the assumption risk — not a flat guess. The worksheet shows the roll-up.
  5. Link to the SoW scope boundary. The breakdown's leaves are the in-scope items; the exclusions are the out-of-scope items; the PERT total + contingency is the fixed-frame price.

Techniques: PERT is the default

Multiple estimation techniques exist; PERT is the favoured system here because three-point estimates make fixed-cost uncertainty explicit and roll up into a defensible contingency.

PERT (three-point) — the default. For each leaf, capture three estimates and weight them:

Expected (TE) = (O + 4·M + P) / 6        SD = (P − O) / 6        Variance = SD²
  • O = optimistic (everything goes right), M = most-likely, P = pessimistic (plausible worst case — not catastrophe).
  • Roll up: engagement TE = Σ leaf TE; engagement SD = √(Σ leaf variances).
  • Size contingency from the rolled-up SD (e.g. a one- or two-SD buffer for the confidence level the fixed frame needs). The worksheet does the arithmetic.

Alternatives (use when they fit better, or to triangulate):

TechniqueUse when
Analogous (top-down, from a similar past engagement)Early, little detail; a quick sanity anchor
Parametric (units × rate, e.g. per source system / per ontology module)The work scales with a countable driver
Bottom-up (sum of leaf estimates)Detail exists; pairs naturally with PERT per leaf

Triangulate when the stakes are high: a PERT bottom-up that disagrees with an analogous top-down is a signal to re-examine the breakdown.

Gantt / scheduling is EXTERNAL

This skill produces the work breakdown + estimates. It does not draw Gantt charts or schedules. Scheduling (dependencies, calendar, resource levelling, the Gantt itself) is rendered in external tools — Smartsheet or MS Project — by importing the work breakdown. Do not attempt to draw Gantts in-repo; produce a clean breakdown that those tools can consume. Sequencing intent (pilot → scale order) comes from decision-package; the calendar rendering of it is the external tool's job.

The checklist

Run before any number leaves the room:

  • Work broken into leaves small enough for a three-point estimate (decomposed against the epic-planning breakdown where build work is involved).
  • Each leaf has O / M / P and a PERT expected value.
  • Variances rolled up; engagement SD computed.
  • Contingency sized from the rolled-up SD + assumption risk (not a flat percentage guess).
  • Assumptions listed; each risky assumption has an exclusion or a stop/extend trigger.
  • Exclusions = the SoW out-of-scope list (the invariant in proposal-writing).
  • Triangulated against at least one alternative technique when the bid is large.
  • Work breakdown exported clean enough for Smartsheet / MS Project to schedule.

The fillable worksheet (PERT table + roll-up + contingency) is in references/pert-worksheet.md; the full checklist is in references/estimation-checklist.md.

Boundary & Related Skills

This skill OWNS: the estimation / scoping discipline — PERT + work breakdown + uncertainty ranges + assumptions/exclusions + contingency, and the clean breakdown that external scheduling tools consume.

This skill DELEGATES:

  • The proposal / SoW wrapper (and the scope-boundary discipline the exclusions feed) → proposal-writing.
  • The build breakdown the estimate decomposes against → epic-planning.
  • Sequencing / roadmap intent (pilot → scale) → decision-package.
  • The calendar/Gantt rendering → external tools (Smartsheet, MS Project) — out of repo.

Related: proposal-writing, epic-planning, decision-package.

Tone & style

British English. Terse and numeric. Every number traces to a leaf, an assumption, and a technique; no unexplained round figures. A point estimate without a range is a smell — show the range and the contingency that covers it.