Generate resource plan

Skill KirKruglov/claude-project-manager/skills/generate-resource-plan

AI Project Manager plugin for Claude Cowork — full project lifecycle automation: charter, plan, risks, budget, monitoring, comms, closure. 21 skills, PMBoK + Agile.

Install
npx -y skills add KirKruglov/claude-project-manager --skill generate-resource-plan

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 5 stars5 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

What its author says it does

Copied from the file, not written here

Generates a resource allocation plan (resource-plan.md) for Phase 2 — Planning, based on project-plan.md and team-list.md. Produces a role-by-phase FTE matrix with person-month calculations, rates (when available), external resources section, and a phase-load summary. Covers task #8 of the project management agent. Mode B: agent prepares draft, PM reviews and approves. Required input for generate-budget (#9). Triggers RU: «составь ресурсный план», «распредели ресурсы по проекту», «кто и когда работает», «ресурсный план проекта», «загрузка команды по фазам», «generate-resource-plan». Triggers EN: 'generate resource plan', 'resource allocation plan', 'create resource plan', 'team allocation by phase', 'staffing plan', 'who works when'.

SKILL.md

9.7 KB, as published. Nobody here has run it

Skill: generate-resource-plan

Generates a resource allocation plan for an IT project during the planning phase (Phase 2). Reads the project plan (phase durations) and team list (roles, FTE, rates), builds a role-by-phase FTE matrix with person-month totals and cost estimates (when rates are available). Output: resource-plan.md — the primary input for generate-budget. Mode B: agent prepares draft, PM reviews.


Triggers

Russian: «составь ресурсный план», «распредели ресурсы по проекту», «кто и когда работает», «ресурсный план проекта», «загрузка команды по фазам», «ресурсы на проект» English: "generate resource plan", "resource allocation plan", "create resource plan", "team allocation by phase", "staffing plan", "who works when", "resource plan"


Language Detection

Determine the language of the user's request:

  • If the request is in Russian → use templates with the -ru suffix, respond in Russian
  • Otherwise → use templates with the -en suffix, respond in English

Input

DataRequiredSource
Project planyes02-planning/project-plan.md
Team listyesinput/team-list.md
Project charterno01-initiation/project-charter.md — project name, PM, GTM scope
Preliminary estimateno01-initiation/preliminary-estimate.xlsx — aggregated team costs by phase (fallback)
Constraintsnoinput/constraints.md — resource or headcount constraints

Output

FileProject pathFormat
resource-plan.md02-planning/.md

File structure — 4 sections (Internal Team, Allocation Matrix, External Resources, Summary) — defined in templates/resource-plan-{lang}.md.


Instructions

Step 1 — Check Dependencies

Guard-rail — check request type. If the request contains language related to budget calculation, cost totals, contingency reserves, financial planning, or total project cost — even alongside a resource plan request — respond: "generate-resource-plan creates a role-by-phase allocation matrix, not a budget. For the project budget use generate-budget (task #9) — it reads resource-plan.md and produces project-budget.xlsx. Run generate-resource-plan first, then generate-budget." Do not start the workflow.

If the request is about task decomposition, sprint planning, or WBS → respond: "generate-resource-plan shows who is allocated at what FTE per phase, not a task breakdown. For task-level planning use generate-project-plan." Do not start the workflow.

Check for required files:

  1. 02-planning/project-plan.md
  2. input/team-list.md

If project-plan.md is not found: Stop. Respond: "A project plan is required to generate the resource plan. Run generate-project-plan (task #7) first — it defines phases, durations, and key activities that drive resource allocation."

If team-list.md is not found: Stop. Respond: "A team list is required to generate the resource plan. Create input/team-list.md with roles, team members, and FTE allocation per phase, then run this skill again."

If both files are found: proceed to Step 2.


Step 2 — Extract Phase Data from project-plan.md

Read 02-planning/project-plan.md and extract:

  • List of phases (Phase 1 through Phase 6, or as defined in the plan)
  • Duration of each phase (in weeks; convert to months: weeks / 4.3, round to 1 decimal)
  • Key activities per phase — used to infer which roles are active
  • Project name and PM (if present) — also check project-charter.md

Record the phase list and durations. This is the column structure for the allocation matrix.


Step 3 — Extract Team Data from team-list.md

Read input/team-list.md and extract:

Internal team (штатные / permanent):

  • Role, name, grade
  • FTE allocation: use the percentage from team-list.md as the base allocation
    • If allocation is given as a single number for the whole project (e.g., "80%") → apply it uniformly across all phases where the role is active
    • If allocation varies by phase or period → record phase-specific values
  • Rates:
    • If rates are given ($/month or ₽/month) → record for cost calculation
    • If rates are "—" or marked as штат/operational budget → record as "—", add note in assumptions: "Internal team salaries are included in the company's operational budget and are not reflected in the project budget."

External resources (contractors, outsource):

  • Role, vendor/name, engagement period, budget (fixed sum), scope of work
  • Map the engagement period to phases from Step 2

From constraints.md (if available):

  • Any headcount limits, FTE caps, or team availability constraints → record in Assumptions.

Step 4 — Build the Allocation Matrix

Construct the FTE allocation matrix: rows = roles, columns = phases.

For each role × phase combination:

  1. Is the role active in this phase?
    • If project-plan.md or team-list.md explicitly states the phase → use it
    • If not explicitly stated: use the general project FTE from team-list.md, assume the role is active in phases where the key activities match the role's competency
    • PM / Project Manager is active across all phases at their stated FTE
  2. Record FTE % per phase (e.g., 0.5 = 50%, 1.0 = 100%, 0 = not active)
  3. Calculate person-months: p-m = FTE × phase_duration_months
    • Round to 1 decimal place
  4. If rate is available: calculate phase_cost = p-m × rate

Row totals: sum of person-months across all phases for each role. Column totals: sum of person-months across all roles for each phase.


Step 5 — Compile Assumptions and Risk Notes

Write the Assumptions section (minimum 3 items):

  1. Data source for phase durations (project-plan.md, which phase structure was used)
  2. FTE allocation logic (uniform vs phase-specific; basis for inference if used)
  3. Rate handling: "Rates taken from team-list.md" OR "Internal team on operational budget — cost columns left blank. External resources: contract amounts as stated in team-list.md"
  4. Any phase-allocation assumptions made by the agent (e.g., "QA assumed active in phases 3–5 based on testing activities in project-plan.md")
  5. If preliminary-estimate.xlsx was used as a fallback for aggregated team cost → state it

Resource risks (if detected):

  • Any role allocated at 100% across multiple overlapping phases → flag as overallocation risk
  • Any role that is the only resource in a critical competency area (e.g., sole developer, sole designer) and is heavily loaded (≥80% FTE) across all phases → flag as single-point-of-failure risk
  • Critical path roles (e.g., sole developer) allocated below 50% on key phases → flag
  • External resource engagement not aligned with phase dates → flag

Step 6 — Create resource-plan.md and Save

Follow the schema in templates/resource-plan-{lang}.md:

  1. Create resource-plan.md in {project}/02-planning/.
  2. Show in chat:
    • Confirmation: "resource-plan.md saved to 02-planning/."
    • Allocation matrix as a markdown table (Section 2 summary).
    • List of assumptions.
    • Resource risk flags (if any).
    • Next step: "Resource plan is ready. Review FTE allocations and correct if needed. Once approved, use generate-budget (task #9) — it reads this file to calculate the project budget."
  3. Write to logs/log.md: date, skill, file created, total person-months, rate coverage (e.g., "rates available for 2/5 roles").
  4. Update project-state.md: artifact resource-plan.md status → "draft".

Templates

FilePurpose
templates/resource-plan-ru.mdArtifact schema (RU)
templates/resource-plan-en.mdArtifact schema (EN)

Dependencies

Reads:

  • 02-planning/project-plan.md — phases, durations, key activities
  • input/team-list.md — roles, FTE allocation, rates, external resources
  • 01-initiation/project-charter.md — project name, PM, GTM scope
  • 01-initiation/preliminary-estimate.xlsx — aggregated team costs (optional fallback)
  • input/constraints.md — resource constraints (optional)

Passes data to:

  • generate-budget (#9) — FTE, rates, person-months per phase → cost calculation

Constraints

  • Mode B: resource plan is a draft for PM review, not a final document
  • Does not build a task schedule or WBS — use generate-project-plan
  • Does not calculate the project budget — use generate-budget
  • FTE values are taken from team-list.md; the skill does not validate them against calendar capacity or workday availability
  • Internal team rates marked "—" are left blank in cost columns — this is intentional
  • Operates on one project per invocation
  • If project-plan.md is unavailable — skill does not run; no fallback