Dod rio
Skill jgsystemsconsulting/jgs-se-knowledge-packs/packs/dod-rio
46 agent knowledge packs distilling vetted, licence-clean systems-engineering standards (NASA, DoD, FAA, NIST, GAO, SEBoK) into on-demand Claude skills.
npx -y skills add jgsystemsconsulting/jgs-se-knowledge-packs --skill dod-rioAssembled from the repository path, not quoted from the project. Check it against their README if it does not work.
2 things to look at
- no licenseNo license file was found in the repository. Code published without one is not open source by default, so using it at work is a question for whoever answers licensing questions where you are.
- 1 stars1 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.
What its author says it does
Copied from the file, not written here
Knowledge base from the DoD Risk, Issue, and Opportunity (RIO) Management Guide for Defense Acquisition Programs (OUSD R&E, Sep 2023 incl. Change 2.2). Use for the defense-acquisition mechanics of program risk management: the RIO definitions (risk/issue/opportunity), the five-step risk process (plan-identify-analyze-mitigate-monitor), 1-5 likelihood/consequence scoring and the 5x5 risk matrix, the four mitigation options (accept/avoid/transfer/control), burn-down plans, issue management (probability=1), opportunity management toward should-cost, cross-program/interface risk, tailoring RIO to the six AAF acquisition pathways (UCA/MTA/MCA/Software/DBS/Services), specialized methods (RMF, MBCRA/Cyber Table Top, Agile metrics, FMECA, ITRA/DTRAM), and institutionalizing RIO via the PRMP, boards (RMB/JRMB/ROMB/RWG), tools, tiered roles, and WBS/IMP/IMS/EVM/TPM integration. This is the DoD-acquisition complement to nasa-risk (general CRM/RIDM theory) and dau-se-guidebook (the SE process frame). Does NOT teach general risk theory from scratch, and defers specialized risk regimes (system safety/ESOH, HSI, detailed cyber/RMF, spectrum) to their own DoD instructions and the relevant packs.
SKILL.md
17.4 KB, as published. Nobody here has run it
DoD Risk, Issue, and Opportunity (RIO) Management Guide
Source: OUSD R&E (US Government work, public domain; Distribution A) | Chapters: 8
When to use
Use this skill to run program risk, issue, and opportunity management on a U.S. defense acquisition program: defining and scoring risks, choosing and burning down mitigations, managing realized issues, hunting opportunities toward should-cost, containing cross-program interface risk, tailoring the whole effort to the chosen Adaptive Acquisition Framework (AAF) pathway, layering in specialized risk methods, and institutionalizing it all through the program's plan, boards, tools, roles, and cost/schedule/technical artifacts. This is the DoD-acquisition rendering of risk management — the program-office mechanics that sit on top of the general continuous-risk-management theory in nasa-risk and inside the SE process frame in dau-se-guidebook.
Prerequisites: none — plain Markdown; no MCP server, API key, or licence tier needed at runtime.
How to Use This Skill
- Without arguments — load the core frameworks below: the three RIO objects, the five-step process, likelihood/consequence scoring and the matrix, the four mitigation options, and the institutional machinery.
- With a topic — ask about a scoring rule (consequence = max-of-three, unmitigated), a mitigation option (accept/avoid/transfer/control), a burn-down plan, issue or opportunity management, cross-program tripwires, an AAF pathway (UCA/MTA/MCA/Software/DBS/Services), or a specialized method (RMF, Cyber Table Top, ITRA/DTRAM, FMECA).
- With a chapter —
ch02(identify + analyze + scoring),ch03(mitigate/monitor/issues),ch04(opportunity + cross-program),ch05/ch06(RIO by AAF pathway),ch08(PRMP/boards/roles/tool integration).
Supporting files: glossary.md, patterns.md, cheatsheet.md.
One discipline, three faces, two complements. Risk, issue, and opportunity are managed as one family with a shared register and shared boards. The guide is guidance, not mandate — recommended practice for AAF programs, used with DoDI 5000.02, not a mandatory checklist. Read it with
nasa-risk(the general method) anddau-se-guidebook(the SE process), which it specializes rather than replaces.
Core Frameworks & Mental Models
The three RIO objects (the diagnostic lens)
The guide reduces the whole domain to three diagnostic questions, each a distinct managed object tied to the cost / schedule / performance baseline:
- Risk — what can go wrong? A possible future event/condition that could harm objectives; characterized by likelihood AND consequence.
- Issue — what has gone, or will certainly go, wrong? A realized or near-certain negative event (likelihood = 5 / probability = 1); characterized by consequence only.
- Opportunity — what can be improved? A potential future benefit; the upside mirror of risk, the engine for reaching should-cost (vs. merely staying inside will-cost).
The central stance: the worth of risk management comes from a PM who thinks critically and grows a risk-aware culture, not from satisfying policy. Plans over process — the individual mitigation plans (the output) matter more than the machinery; drop any step that doesn't add value, and never "shoot the messenger."
The five-step risk process
Plan → Identify → Analyze → Mitigate → Monitor
└────────── continuous Communication & Feedback ──────────┘
The same steps apply across every life-cycle phase and every AAF pathway; only the detail of each action changes. The PM owns it (jointly led with the LSE); it is multidisciplinary (SE, T&E, EVM, production, QA, logistics) and runs top-down and bottom-up at once.
Scoring: 1–5 ordinal, max-of-three, unmitigated
- Likelihood 1–5 against probability bands (Table 2-2); consequence 1–5 against tailored criteria (Table 2-1, anchored to the MCA pathway).
- Consequence = the maximum of cost/schedule/performance impact — never an average — assessed as if fully realized with no further mitigation, using fully burdened costs. A KPP/APB threshold breach forces Level 5.
- No fractional scores (2.4 is invalid). Government and contractor use a common framework so disagreements are visible and comparable, not forced into consensus.
- The 5×5 risk matrix maps likelihood × max-consequence to Low (green)/Moderate (yellow)/High (red). Risk level ≠ priority — also weigh cost-effectiveness, time frame, inter-risk relationships, and EMV/ROI, but always rank KPP-threatening risks high. Model aggregate exposure with Monte Carlo SRA/CRA.
- The risk register (built early) is the single source of truth; risk/issue/opportunity registers may be combined.
The four mitigation options
Every controlled risk gets Accept · Avoid · Transfer · Control (or a hybrid):
| Option | Essence | Watch-out |
|---|---|---|
| Accept | Bear it but keep tracking (Watch Item) | Pre-identify resources if realized; acceptance ≠ ignoring |
| Avoid | Alternate path / defer / substitute mature tech | Defer only if system would ship without it |
| Transfer | Reassign (MOA/MOU) | Hardest; never fully removes Government exposure |
| Control | Drive likelihood/consequence down | Default; must be real reduction, not relabeled baseline work |
A burn-down plan (six steps) makes a Control plan trackable: sequence → make objective/measurable → assign planned L/C → date → load into IMS → chart level vs. time. Required for all high/moderate and selected low risks. Meetings don't burn down risk — results do. Front-load high-consequence risks.
Issues and opportunities (the mirrors)
- Issue management mirrors the risk loop but drops the likelihood axis (probability = 1): score consequence, assign an RMB owner, plan a corrective action / POA&M with an EAC in the IMS, re-assess for spawned risks. Options are mainly Ignore (after a business case) or Control.
- Opportunity management is the proactive twin: a six-activity loop (plan → identify → analyze [business case] → decide → monitor → feedback), with options Pursue / Defer / Reevaluate / Reject. Spending effort raises the likelihood of a good event (the inverted lever). Aggregate small wins; reject short-term-gain/long-term-loss candidates.
Cross-program / interface risk
When a system depends on hardware/software/schedules owned by other programs, the interfaces are a primary risk source owned by no one. Contain with a designated technical authority, MOAs carrying cost/schedule/performance tripwires, an ICWG, ICDs/IRSs, synchronized schedules, an integration plan, and giver–receiver deliverables tracked in the IMS. Escalate early up PM → PEO → SAE → DAE; refer requirements disputes to the CSB. Reconcile SWAP-C across the seam.
RIO is tailored to the AAF pathway
There is no single DoD risk process — the pathway pre-sets the risk posture, and tailoring is fine adjustment:
- UCA (<2 yr, DoDI 5000.81) — accepts deficiencies for speed; ends in a disposition analysis.
- MTA (2–5 yr, DoDI 5000.80) — fails early and descopes; op demo ≥1 yr before completion.
- MCA (milestone-driven, DoDI 5000.85) — front-loads hard decisions, picks the entry milestone by where risk lives, burns down Technology/Engineering/Integration risk in TMRR while money is cheap, and gates with SETRs (ASR/SRR/SFR/PDR → CDR/TRR/SVR/FCA/PRR → OTRR/IOT&E/PCA) plus TRA/MRA/SRA.
- Software (DoDI 5000.87) — automation/continuous-test/cyber up front; MVP→MVCR; User Agreement; technical-debt tracking.
- DBS (DoDI 5000.75) — fit a commercial product to re-engineered processes via fit-gap; ATP gates.
- Services (DoDI 5000.74) — the requirement is the risk; seven steps, ARRT→PWS/QASP, CPARS.
Contract type follows the risk profile — risk is never fully transferred to industry (the Government still needs the product).
Specialized methods feed the enterprise register
Each is a sensor for a risk class the general process won't surface; funnel each back into one register with a common consequence language (roll micro-risks up, decompose macro-risks down): RMF (DoDI 8510.01; 7 steps; tiered per NIST SP 800-39), MBCRA / Cyber Table Top (DoDI 5000.89; mission-framed cyber), Agile metrics (Size/Time/Effort/Defects), FMECA on the digital model (DoDI 5000.88), ITRA/DTRAM (8 risk areas × 7 factors), and S&T/program protection (DoDI 5000.83).
Institutionalization
RIO becomes durable machinery: the PRMP (written at formulation, refreshed at life-cycle events); boards — PM-chaired RMB, JRMB for mutual Government–contractor risk, ROMB when it also handles opportunities, chartered RWGs; an early, SEP-documented tool (Project Recon / Active Risk Manager / Risk Exchange); tiered roles with the non-negotiable rule that every risk has an owner; and traceability into WBS (MIL-STD-881F), IMP/IMS, EVM (EIA-748), and TPMs (DoDI 5000.02, kept SMART). A mitigation not tied to a funded work package and a schedule activity is aspiration, not management.
Chapter Index
| # | Section | Key content |
|---|---|---|
| ch01 | RIO Foundations | Purpose/scope; risk vs. issue vs. opportunity definitions; guidance-not-mandate; PM ownership; plans-over-process; deferred specialized regimes |
| ch02 | Risk: Plan, Identify, Analyze | Five-step process; PRMP/SEP; risk categories (Technical/Programmatic/Business); risk statement; 1–5 scoring; risk matrix; register; EMV; aggregate/Monte Carlo |
| ch03 | Mitigation, Monitoring & Issues | Four options (accept/avoid/transfer/control); six-step burn-down; monitoring against EVM/IMS/TPM; issue management (probability = 1) |
| ch04 | Opportunity & Cross-Program | Opportunity loop and should-cost; opportunity register; RMB/ROMB; interface risk; MOAs/tripwires; ICWG; SWAP-C; escalation chain |
| ch05 | RIO by AAF Pathway (UCA/MTA/MCA) | Pathway as pre-set risk dial; MCA entry-by-risk; SETR gates; TRA/MRA/SRA; framing assumptions; contract type; disposition analysis |
| ch06 | RIO by AAF Pathway (Software/DBS/Services) | Software pipeline/MVP→MVCR/User Agreement; DBS fit-gap and ATP gates; Services seven steps/ARRT/QASP/CPARS |
| ch07 | Additional Methods | RMF (7 steps, NIST 800-39 tiers); MBCRA/Cyber Table Top; Agile metrics (Size/Time/Effort/Defects); Digital Engineering/FMECA; ITRA/DTRAM; S&T protection |
| ch08 | Process, Roles & SE/PM Tools | PRMP outline; RMB/JRMB/ROMB/RWG; Service tools; tiered roles; WBS/IMP/IMS/EVM/TPM integration; SRA/CRA/PRA; DCMA 14-point; UAV-jammer example |
Topic Index
- AAF pathways (selecting/tailoring) → ch05, ch06, cheatsheet
- Aggregate / compounding risk (Monte Carlo) → ch02, ch08
- Burn-down plan / chart → ch03, ch08, cheatsheet
- Business / External risk → ch02
- Consequence (max-of-three, unmitigated, fully burdened) → ch02, cheatsheet
- Contract type as a risk instrument → ch05, ch08
- Cross-program / interface risk; MOAs; tripwires; ICWG; SWAP-C → ch04
- Cyber Table Top (CTT) / MBCRA → ch07, ch06
- DCMA 14-point schedule metrics / schedule health → ch08
- Digital Engineering / FMECA → ch07
- DTRAM (8 areas × 7 factors) / ITRA → ch07
- EMV / ROI prioritization → ch02
- Escalation chain (PM→PEO→SAE→DAE) / CSB → ch04
- Framing assumptions → ch05
- Issue management (probability = 1; Ignore/Control; POA&M/EAC) → ch03
- Likelihood (1–5 bands) → ch02
- Mitigation options (accept/avoid/transfer/control) → ch03, cheatsheet
- Monitoring (EVM/IMS/TPM, trend matrix) → ch03, ch08
- Opportunity management / should-cost vs. will-cost → ch04, cheatsheet
- PRMP (plan, outline, refresh triggers) → ch01, ch02, ch08
- Risk vs. issue vs. opportunity (definitions) → ch01, cheatsheet
- Risk categories (Technical/Programmatic/Business) → ch02
- Risk matrix (5×5) → Low/Moderate/High → ch02, cheatsheet
- Risk register (single source of truth, combined) → ch02, ch08
- Risk statement (event+consequence+cause; if–then) → ch02
- RMB / JRMB / ROMB / RWG (boards & working groups) → ch02, ch03, ch08
- RMF (7 steps; Assess Only; NIST SP 800-39 tiers) → ch07
- Roles (Executive/Management/Working; every risk has an owner) → ch08
- SETRs (ASR/SRR/SFR/PDR/CDR/TRR/SVR/FCA/PRR/OTRR/PCA) → ch05
- Software pathway (MVP→MVCR, User Agreement, technical debt) → ch06
- SRA / CRA / PRA (indicators, not verdicts) → ch08, ch02
- Tailoring (drop steps that don't add value) → ch01, ch05
- Tools (Project Recon / Active Risk Manager / Risk Exchange) → ch08
- TRA / MRA (readiness assessments) → ch05
- WBS / IMP / IMS / EVM / TPM integration → ch08
Supporting Files
- glossary.md — RIO terms (boards, scores, pathways, tools, methods), alphabetical, with chapter references
- patterns.md — 11 reusable techniques (write a risk statement, score, classify, pick a mitigation, build a burn-down, manage issues/opportunities, contain cross-program risk, tailor to pathway, funnel specialized methods, institutionalize) with When/How/Trade-offs
- cheatsheet.md — the three RIO objects, scoring rules, mitigation/issue/opportunity options, AAF pathway → posture table, specialized-methods table, institutionalization, and tells & smells
Scope & Limits
Covers: program risk, issue, and opportunity management for U.S. defense acquisition programs per the DoD RIO Management Guide (Sep 2023, incl. Change 2.2) — the RIO definitions; the tailorable five-step risk process; 1–5 likelihood/consequence scoring, the 5×5 matrix, EMV/ROI, and aggregate Monte Carlo analysis; the four mitigation options and the six-step burn-down; issue management (probability = 1); opportunity management toward should-cost; cross-program/interface risk; RIO tailoring across all six AAF pathways; the specialized methods (RMF, MBCRA/CTT, Agile metrics, DE/FMECA, ITRA/DTRAM, S&T protection) as risk sensors; and institutionalization via the PRMP, boards, tools, tiered roles, and WBS/IMP/IMS/EVM/TPM integration.
Does not cover in depth (deferred by the source to its own authorities): general risk theory and continuous-risk-management method built from scratch (use nasa-risk); the broader SE process model RIO sits inside (use dau-se-guidebook); system safety / ESOH and hazard analysis (DoDI 5000.88, MIL-STD-882 — see mil-std-882 / system-safety packs); Human Systems Integration (DoDI 5000.95 — see nasa-hsi); the full cybersecurity RMF control workflow and SP 800-53 catalog (DoDI 8510.01 / NIST — see nist-800-37, nist-sse); electromagnetic spectrum/E3 (DoDI 4650.01 / 3222.03); Technology Readiness Assessment depth (see gao-tra); and modular-open-systems detail (see dod-mosa). It is guidance, not mandatory policy, and is thin on worked numeric examples beyond the single Appendix-D UAV-jammer walkthrough.