BA Phase 4 — iteration dispatch planning. Load after Phase 2 sign-off when Phase 1.Z produced a non-empty SRS diff (the dispatch is an iteration, not a first-time ingest). Runs the concurrent-iteration guard, magnitude check, optional cleanup-task prompt, and produces docs/iteration-plan/v<new>.md (the surgical re-dispatch matrix the Orchestrator consumes at §9 Step 3.5).From its SKILL.md

Install
npx -y skills add evolplus/talos --skill ba-iteration-planning

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 8 stars8 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

SKILL.md

11.4 KB, as published. Nobody here has run it

BA Phase 4 — Iteration Dispatch Planning

When to use

You are the BA and an iteration was confirmed: Phase 2 signed off the new SRS version and Phase 1.Z (in the ba-ingestion-pipeline skill) produced a non-empty diff at docs/srs-diffs/. Produce the surgical re-dispatch plan the Orchestrator consumes. Includes the concurrent-iteration guard, magnitude check, and cleanup-task prompt.

Phase 4 — Iteration Dispatch Planning

This phase runs after Phase 2 sign-off AND only when Phase 1.Z produced a non-empty diff (the dispatch is an iteration, not first-time ingest). It produces the surgical re-dispatch plan the Orchestrator consumes at §9 Step 1.5.

Step 0 — Concurrent-iteration guard

Before any other Phase 4 work, scan docs/iteration-plan/ for any file with Processed-by-orchestrator: false. The kit's iteration model assumes one iteration in flight at a time — overlapping iteration plans produce undefined behavior (matrix #2 may reference tasks that matrix #1 just cancelled, agents may receive stale dispatch context, etc.).

If at least one unprocessed iteration plan exists, halt with NEEDS_CONTEXT:

Status: NEEDS_CONTEXT
Reason: An earlier iteration plan is still in flight.
Question: Found <N> unprocessed iteration plan(s): <list paths>. Cannot safely start a new iteration v<new> while these are unresolved (task transitions from the earlier matrix may conflict with the new one). How do you want to proceed?
Options:
  [a] Wait — pause the new iteration here; complete the in-flight plan(s) (Orchestrator §9 Step 3.5 processes them), then re-dispatch this iteration. SAFEST.
  [b] Abandon the in-flight plan(s) — mark each as Processed-by-orchestrator: true with an `Abandoned: <reason>` line in the plan's changelog. Risky: any agent mid-task from the earlier plan must be halted manually first; tasks transitioned by the earlier plan stay in their transitioned state. Use only when the earlier plan is verifiably stale or wrong.
  [c] Cancel the new iteration — discard the incoming SRS changes; project stays at v<old>.
Recommended: a
Confidence: high
Justification: Concurrent iterations have no defined precedence in the kit's master-plan-discipline. Waiting is the only path that guarantees consistent task state.

Only when the response is [a] (after the earlier plan flips to Processed-by-orchestrator: true) or [b] (with explicit abandonment cost accepted) may Phase 4 proceed to Step 1. Option [c] ends Phase 4 with no plan produced; revert SRS Status to the prior Signed-off state and file a deferred open-issue.

Step 1 — Magnitude check

Before producing the dispatch plan, run a magnitude check against the diff. Any of these conditions triggers a halt + NEEDS_CONTEXT:

ThresholdTrigger conditionDefault
US-modification ratio# modified US-IDs / # total US-IDs in current SRS> 30%
FR-modification ratiosame on FR-IDs> 50%
US deprecation count# US-IDs moved to ## Deprecated in this iteration> 5
Domain rewriteAny change in SRS §3.1 (Bounded Context, Aggregate Root, Entities, Value Objects, Ubiquitous Language)any change
Security expansionNew sub-category added to §4.1 Security & Complianceany add
NRS tighteningQuantitative target tightened by more than 2× (e.g., P95 1000ms → 200ms = 5×)> 2× tighten
Cross-task impactTasks in done state affected by modified US/FR> 10 tasks

If ANY threshold triggers, halt with NEEDS_CONTEXT before producing the iteration plan:

Status: NEEDS_CONTEXT
Reason: Iteration magnitude exceeds threshold — high re-work risk.
Question: The proposed iteration v<old> → v<new> exceeds magnitude guardrails on: <list of triggered thresholds with numbers>. This level of change risks breaking the current system and forcing wide re-work. How do you want to proceed?
Options:
  [a] Proceed anyway — accept the re-work scope; BA produces the iteration plan; Orchestrator dispatches per the matrix.
  [b] Split into smaller iterations — PM revises the incoming SRS into versions v<old>.1, v<old>.2 etc., each within thresholds; BA re-ingests each smaller version separately.
  [c] Cancel iteration — discard incoming SRS; project stays at v<old>.
Recommended: b
Confidence: high
Justification: <which thresholds triggered, with the numbers — e.g., "52% US modified (16/31), exceeds 30% threshold; 14 done tasks affected, exceeds 10 threshold">

The recommendation defaults to [b] split because iterations within thresholds have predictable cycle-time; iterations outside have unpredictable rework cascades. Only after the user picks does Phase 4 continue.

Step 1.5 — Cleanup task prompt (optional, fires only when deprecations exist)

After magnitude check passes and BEFORE producing the iteration plan, check whether the diff deprecates any US-IDs or FR-IDs whose linked tasks are in done state (i.e., shipped code will become orphaned).

If at least one such case exists, halt with NEEDS_CONTEXT to ask whether to add cleanup task(s):

Status: NEEDS_CONTEXT
Reason: This iteration deprecates work that has already shipped. Cleanup tasks are optional and your call.
Question: <N> shipped task(s) will transition to `done-deprecated`: <list of T-IDs with the deprecated US/FR each linked to>. The implementation persists in the codebase until a cleanup task removes it. Add cleanup task(s) to this iteration plan?
Options:
  [a] Yes, add cleanup task(s) — TL appends a cleanup task per affected component (or one bundled cleanup task if the implementations share a module). Code is removed, dead routes / endpoints / UI screens decommissioned. RECOMMENDED for most projects.
  [b] No, leave the implementation in place — useful when the deprecated behavior is still needed for analytics, backward-compatibility, or to keep historical user data accessible. The code stays; QA-Exec still skips the deprecated test cases via the `deprecated-us` Pre-Run check.
  [c] Defer the decision — add a deferred open-issue (`State: deferred`, `Target phase: after current iteration completes`) tracking the cleanup question; iteration plan is produced without cleanup tasks; the question is answered in a future BA dispatch.
Recommended: a
Confidence: medium
Justification: Most projects accumulate cruft when cleanup is deferred; explicit `[a]` plus a tracked cleanup task is usually cheapest in the long run. Pick `[b]` deliberately when retention is the design intent, not when cleanup is hard.

User picks one:

  • [a] add: include cleanup task rows in the iteration plan's re-dispatch matrix (one row per affected component, dispatched to TL who adds the task to the current phase or a new cleanup phase).
  • [b] no: skip cleanup; the affected tasks transition to done-deprecated but no new cleanup task is added. Note the [b] choice in the iteration plan's metadata so future audits can reconstruct the decision.
  • [c] defer: open-issue filed; iteration plan produced without cleanup; the question persists.

No prompt fires when the iteration has zero done-state affected tasks (e.g., all deprecations are of US-IDs whose tasks were still not-started or in-progress, which transition to cancelled regardless and have no shipped code to clean up).

Step 2 — Produce iteration plan

Once thresholds are within bounds OR user accepted [a] proceed anyway, produce docs/iteration-plan/v<new-version>.md:

# Iteration plan — v<old> → v<new>

- Diff source: docs/srs-diffs/v<old>-to-v<new>.md
- Generated: <ISO-8601>
- Concurrent-iteration check: clean (no in-flight plans) | abandoned-prior (cite which plan paths + abandon reason)
- Magnitude check: passed | overridden-by-user (cite NEEDS_CONTEXT timestamp + chosen option)
- Cleanup decision: yes-add (cite cleanup task IDs below) | no-leave-in-place (cite NEEDS_CONTEXT timestamp) | deferred (cite open-issue ID) | n/a (no done-state deprecations in this iteration)

## Re-dispatch matrix

One row per change × agent × scope. The Orchestrator dispatches each row's agent against the cited scope.

| Change | Agent | Scope | Trigger |
|---|---|---|---|
| US-NNN modified (BR-N changed) | SA | re-check architecture for impact on this US's component | architecture review only if affected |
| US-NNN modified | QA-Author | by-us re-run for US-NNN only (regen `docs/test-cases/by-us/US-NNN/functional.md`) | functional.md regen |
| US-NNN modified | TL | re-evaluate tasks linked to US-NNN; modify DoD, add new tasks, mark obsolete tasks `cancelled` | master-plan delta |
| FR-NNN new (auth endpoint) | SA | extend architecture for new component | full new design path |
| FR-NNN new | TL | new phase or new tasks appended | append to master plan |
| FR-NNN modified (schema changed) | BE Dev | revise frozen contract at `docs/api-contracts/<endpoint>.md`; mark Status: Draft pending re-freeze | contract re-freeze |
| FR-NNN modified | FE Dev | re-implement consumers of changed contract | FE adaptation |
| US-NNN deprecated | TL | transition linked tasks to `cancelled` (if in-flight) or `done-deprecated` (if completed) | task transition |
| US-NNN deprecated (cleanup chose `yes-add`) | TL | append one cleanup task per affected component (or one bundled task if components share a module) to current phase or new cleanup phase; cleanup task DoD: "obsolete code paths removed, dead routes / endpoints / UI screens decommissioned" | cleanup task creation |
| US-NNN deprecated | QA-Author | mark `docs/test-cases/by-us/US-NNN/` files Deprecated (frontmatter `Status: Deprecated`); keep in place | test-case status flag |
| NRS target tightened (P95 1000ms → 200ms) | SA | re-evaluate architecture for new perf target; may write new ADR | architecture review |
| NRS target tightened | QA-Exec | re-run perf tests against new threshold | performance re-test |

## Affected tasks

| Task ID | Current status | Change | New status |
|---|---|---|---|
| T-NNN | done | US-NNN modified — re-test against new BR-2 | re-opened for re-QA (transitions: done → in-test) |
| T-NNN | in-progress | US-NNN deprecated | cancelled |
| T-NNN | done | US-NNN deprecated | done-deprecated |
| T-NNN | not-started | FR-NNN new — add this task | not-started (new) |

## Magnitude metrics

For audit / future-iteration tuning:

- US modification ratio: <X/Y> = <Z%>
- FR modification ratio: <X/Y> = <Z%>
- US deprecation count: <N>
- Done tasks affected: <N>
- NRS tightening ratio (max): <ratio>
- Domain spec changed: yes | no
- Security categories added: <N>

## Processed flag

- Processed-by-orchestrator: false

The Orchestrator flips Processed-by-orchestrator: true after it has dispatched every agent in the re-dispatch matrix. Subsequent BA dispatches see the flag and skip the iteration logic (the plan is already in flight).

Step 3 — plan-update.json for Phase 4

Emit plan-update.json with track: "ba" and notes: "Phase 4 iteration plan produced for v<new>; <N> agent re-dispatches queued". The Orchestrator reads this and proceeds to §9 Step 1.5 (iteration plan consumption) before any other task discovery.