Generate project status report for leadership in RAG formatFrom its SKILL.md
npx -y skills add bromso/metapowers --skill status-reportAssembled from the repository path, not quoted from the project. Check it against their README if it does not work.
One thing to look at
- 1 stars1 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.
SKILL.md
4.7 KB, ~1.0k tokens by cl100k_base, as published. Nobody here has run it
Status Report
Generate a project status report for "$ARGUMENTS" in RAG format (Red/Amber/Green) suitable for leadership review. Summarize progress against milestones, highlight risks and issues, note upcoming milestones, and list asks from leadership.
Prerequisites
None — this is a utility skill. It can be run at any time, with or without existing project artifacts.
If .project/$ARGUMENTS/ exists, read any available artifacts for context. If it does not exist, proceed based on information the user provides.
Process
-
Read existing context:
- If
.project/$ARGUMENTS/exists, read all available artifacts for comprehensive context:- Project charter, roadmap, and backlog for planned scope and milestones
- Sprint data for recent progress and velocity
- Risk assessments for known risks
- Decision logs for recent decisions
- Previous status reports for trend comparison
- If no artifacts exist, gather the information from the user through targeted questions
- If
-
Set overall RAG status with justification:
- Green — on track: project is progressing as planned, no significant risks or blockers, timeline confidence is high
- Amber — challenges but manageable: some risks or issues exist but have mitigation plans, timeline may slip slightly, needs monitoring
- Red — blocked or at-risk: significant blockers or risks threatening delivery, timeline is at serious risk, needs leadership attention or intervention
- Provide a one-line justification for the status: "Green: delivering on schedule with all milestones met this period"
- If the status has changed from the previous report, explain why
- Be honest — do not default to Green to avoid difficult conversations
-
Summarize progress against milestones:
- For each milestone or major deliverable:
- Status — completed, in progress, not started, at risk, blocked
- % complete — estimated progress
- Key accomplishments this period — what was delivered or achieved since last report
- Highlight any milestones that slipped and explain why
- Note velocity trends: is the team accelerating, maintaining, or slowing down?
- For each milestone or major deliverable:
-
List top 3 risks and issues:
- Distinguish between risks (potential problems) and issues (current problems)
- For each:
- Description — what is the risk or issue
- Impact — what happens if it materializes or is not resolved
- Mitigation — what is being done about it
- Owner — who is responsible for managing it
- Limit to top 3 — leadership does not need an exhaustive list, they need the critical items
- If there are more than 3, note "N additional risks tracked in the risk register"
-
Note upcoming milestones and timeline confidence:
- List the next 2-3 milestones with target dates
- For each, state confidence level: high (>80% likely on time), medium (50-80%), low (<50%)
- If any milestone is at medium or low confidence, briefly explain why
- Note any dependencies on external teams, vendors, or decisions
-
List asks and decisions needed from leadership:
- Be specific: "We need approval for X by [date]" or "We need a decision on Y to unblock Z"
- For each ask, explain: what is needed, why, by when, and what happens if it is delayed
- Limit to 2-3 actionable asks — this is the most important section for leadership
- If there are no asks, explicitly state "No asks this period"
-
Include team capacity note:
- Is the team fully staffed or are there gaps?
- Note any planned or unplanned absences that affect delivery
- Flag if the team is at capacity and new work cannot be absorbed without deprioritizing something
- Note upcoming capacity changes (new hires, departures, leaves)
-
Write the artifact — save to
.project/$ARGUMENTS/status-report.md:- Report Date — date of this report
- Overall Status — RAG indicator with one-line justification
- Progress Summary — milestone status with % complete and key accomplishments
- Risks & Issues — top 3 with impact, mitigation, and owner
- Upcoming Milestones — next 2-3 milestones with dates and confidence levels
- Asks from Leadership — specific requests with deadlines
- Team Capacity — staffing and availability notes
- Trend — comparison with previous report status if available
Output
Status report saved to .project/$ARGUMENTS/status-report.md. Present a summary highlighting:
- Overall RAG status with justification
- Key accomplishment this period
- Top risk or issue requiring attention
- Most urgent ask from leadership (if any)