Overall Equipment Effectiveness calculation and analysis skill with availability, performance, and quality trackingFrom its SKILL.md

Install
npx -y skills add a5c-ai/babysitter --skill oee-calculator

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

SKILL.md

3.6 KB, 811 tokens by cl100k_base, as published. Nobody here has run it

OEE Calculator

Overview

The OEE Calculator skill provides comprehensive capabilities for calculating and analyzing Overall Equipment Effectiveness. It supports availability, performance, and quality tracking, six big loss categorization, and world-class benchmarking.

Capabilities

  • Availability calculation
  • Performance rate tracking
  • Quality rate measurement
  • OEE trending and dashboards
  • Six big loss categorization
  • Pareto of losses
  • Improvement target setting
  • World-class benchmarking

Used By Processes

  • LEAN-001: Value Stream Mapping
  • SIX-002: Statistical Process Control Implementation
  • CI-003: Benchmarking Program

Tools and Libraries

  • MES integration
  • OEE software
  • Real-time dashboards
  • Data collection systems

Usage

skill: oee-calculator
inputs:
  equipment: "CNC Machine 5"
  period: "2026-01-15"
  shift_data:
    planned_production_time: 480  # minutes
    downtime:
      - type: "breakdown"
        minutes: 30
      - type: "changeover"
        minutes: 20
    ideal_cycle_time: 0.5  # minutes per unit
    total_count: 800  # units
    good_count: 780  # units
outputs:
  - oee_score
  - availability
  - performance
  - quality
  - loss_breakdown
  - improvement_opportunities
  - trend_analysis

OEE Calculation

Formula

OEE = Availability x Performance x Quality

Where:
Availability = Run Time / Planned Production Time
Performance = (Total Count x Ideal Cycle Time) / Run Time
Quality = Good Count / Total Count

Example Calculation

Planned Production Time: 480 minutes
Downtime: 50 minutes
Run Time: 430 minutes
Ideal Cycle Time: 0.5 minutes
Total Count: 800 units
Good Count: 780 units

Availability = 430 / 480 = 89.6%
Performance = (800 x 0.5) / 430 = 93.0%
Quality = 780 / 800 = 97.5%

OEE = 89.6% x 93.0% x 97.5% = 81.3%

Six Big Losses

Loss CategoryOEE FactorExamples
BreakdownsAvailabilityEquipment failures
Setup/AdjustmentsAvailabilityChangeovers, warm-up
Small StopsPerformanceJams, minor issues
Reduced SpeedPerformanceRunning below ideal rate
Startup RejectsQualityScrap during start-up
Production RejectsQualityIn-process defects

OEE Benchmarks

OEE LevelClassificationTypical Range
World ClassBest in class85%+
GoodAbove average70-85%
AverageTypical60-70%
LowNeeds improvement40-60%
PoorSignificant issues<40%

World-Class Targets

FactorWorld ClassTypical
Availability>90%85%
Performance>95%90%
Quality>99.9%98%
OEE>85%60%

Loss Analysis Process

  1. Collect accurate loss data
  2. Categorize by six big losses
  3. Create Pareto chart
  4. Focus on top losses
  5. Apply appropriate methodology
  6. Track improvement

Integration Points

  • Manufacturing Execution Systems
  • PLC/SCADA systems
  • Quality Management Systems
  • Maintenance management (CMMS)

What ships with it

Read from the repository

Just SKILL.md. No reference files, no scripts.