Sprint planner

Skill 8-bit-sheep/code-harness-skills/skills/sprint-planner

Analyze design docs, calculate velocity from recent work, and create realistic sprint plans with day-by-day breakdowns. Use when user asks to "plan sprint", "create sprint plan", or wants to estimate development timeline.From its SKILL.md

Install
npx -y skills add 8-bit-sheep/code-harness-skills --skill sprint-planner

Assembled from the repository path, not quoted from the project. Check it against their README if it does not work.

One thing to look at

  • 3 stars3 stars. Stars are a popularity signal and not a quality one, but at this level it is likely that nobody has read this closely except its author, and you would be relying on your own review.

SKILL.md

11.0 KB, as published. Nobody here has run it

Sprint Planner

Create comprehensive, data-driven sprint plans by analyzing design documentation, current implementation status, and recent velocity.

Configuration

Environment VariableDefaultDescription
SPRINT_STATE_DIR.sprint-stateDirectory for sprint JSON progress files
DESIGN_DOCS_DIRdesign_docsRoot directory for design documents
CHANGELOG_PATHCHANGELOG.mdPath to changelog file
BUILD_CMDmake buildCommand to build the project
TEST_CMDmake testCommand to run tests
LINT_CMDmake lintCommand to run linting

Quick Start

Most common usage:

# User says: "Plan the next sprint based on the v2.0 roadmap"
# This skill will:
# 1. Read design doc (design_docs/planned/v2-roadmap.md)
# 2. Analyze CHANGELOG for recent velocity
# 3. Review current implementation status
# 4. Propose realistic milestones with LOC estimates
# 5. Create day-by-day task breakdown

When to Use This Skill

Invoke this skill when:

  • User says "plan sprint", "create sprint plan", "plan next phase"
  • User asks to estimate timeline for a feature or design doc
  • User wants to know how long implementation will take
  • User needs to prioritize work for upcoming development

Role in Long-Running Agent Pattern

sprint-planner acts as the "Initializer" agent in the two-phase pattern from Anthropic's long-running agent article:

  • Initializer (sprint-planner): Creates infrastructure for execution

    • Analyzes design docs and calculates velocity
    • Creates markdown sprint plan (human-readable)
    • Creates JSON progress file (machine-readable)
    • Sets up session resumption infrastructure
    • Sends handoff message to sprint-executor
  • Coding Agent (sprint-executor): Works incrementally across sessions

    • Reads JSON progress file on each session start
    • Updates only passes field as milestones complete
    • Can pause/resume work across multiple sessions

This separation enables multi-session continuity - sprints can span days or weeks with the agent resuming work from where it left off.

Available Scripts

scripts/analyze_velocity.sh [days]

Analyze recent development velocity from CHANGELOG and git commits.

Usage:

# Analyze last 7 days (default)
scripts/analyze_velocity.sh

# Analyze last 14 days
scripts/analyze_velocity.sh 14

scripts/create_sprint_json.sh <sprint_id> <sprint_plan_md> [design_doc_md]

Create structured JSON progress file for multi-session sprint execution.

Usage:

scripts/create_sprint_json.sh \
  "M-S1" \
  "${DESIGN_DOCS_DIR:-design_docs}/planned/v2_0/m-s1-sprint-plan.md" \
  "${DESIGN_DOCS_DIR:-design_docs}/planned/v2_0/m-s1-feature.md"

What it does:

  • Creates ${SPRINT_STATE_DIR:-.sprint-state}/sprint_<id>.json with feature list
  • Implements "constrained modification" pattern (only passes field changes)
  • Enables session resumption via structured state
  • Extracts milestones from sprint plan markdown automatically
  • Discovers linked GitHub issues from design doc references

Sprint Planning Workflow

CRITICAL: Always end by handing off to sprint-executor after user approval!

1. Read and Analyze Design Document

Input: Path to design doc (e.g., design_docs/planned/v2-roadmap.md)

What to extract:

  • Completed milestones (marked with checkmarks)
  • Remaining milestones (marked as pending)
  • Target metrics (LOC estimates, timeline, acceptance criteria)
  • Dependencies between milestones

2. Review Current Implementation Status

Check these sources:

  • ${CHANGELOG_PATH:-CHANGELOG.md} - Recent features and LOC counts
  • git log --oneline --since="1 week ago" - Actual commits
  • Design doc vs reality - gaps or partial implementations

3. Analyze Recent Velocity

Use the velocity script:

scripts/analyze_velocity.sh

Calculate:

  • LOC per day from recent milestones
  • Average milestone duration
  • Actual completion rate vs estimates

4. Identify Remaining Work

List incomplete milestones with:

  • Dependencies (what blocks what)
  • Estimated effort (from design doc)
  • Priority (based on dependencies, critical path)
  • Current velocity (can we realistically do this?)

5. Propose Sprint Plan

Use the template: See resources/sprint_plan_template.md

Include:

  • Sprint Summary: Goal, duration, key deliverables
  • Milestone Breakdown: For each milestone:
    • Name and description
    • Estimated LOC (implementation + tests)
    • Dependencies
    • Acceptance criteria
    • Risk factors
  • Task List: Day-by-day breakdown (if < 1 week) or weekly (if longer)
  • Success Metrics:
    • Test coverage target
    • Docs to update

6. Present for Feedback

Show user:

  • Proposed milestones with estimates
  • Assumptions made
  • Areas where input is needed
  • Realistic timeline based on actual velocity

Be ready to revise based on user priorities or constraints.

7. Finalize and Document

Once approved:

# Create sprint plan document (markdown - human-readable)
# Naming: M-<type><number>.md (M-P1 for parser, M-T1 for types, etc.)

Create JSON progress file (machine-readable):

scripts/create_sprint_json.sh \
  "<sprint-id>" \
  "${DESIGN_DOCS_DIR:-design_docs}/planned/<sprint-id>-plan.md" \
  "${DESIGN_DOCS_DIR:-design_docs}/planned/<feature>-design.md"

8. MANDATORY: Populate JSON with Real Milestones

The script creates a TEMPLATE - you MUST populate it with real data!

Required edits to ${SPRINT_STATE_DIR:-.sprint-state}/sprint_<id>.json:

  1. Replace placeholder features array with real milestones:

    "features": [
      {
        "id": "M1_ACTUAL_NAME",
        "description": "Real description from your sprint plan",
        "estimated_loc": 150,
        "dependencies": [],
        "acceptance_criteria": [
          "Actual criterion from sprint plan",
          "Another real criterion"
        ],
        "passes": null,
        "started": null,
        "completed": null,
        "notes": null
      }
    ]
    
  2. Update velocity estimates to match your sprint plan

Validation checklist before handoff:

  • No milestone has "id": "MILESTONE_ID" (placeholder)
  • Each milestone has real acceptance criteria (not "Criterion 1")
  • estimated_total_loc matches sum of milestone LOC
  • estimated_days matches sprint plan duration
  • At least 2 milestones defined

sprint-executor will REJECT the sprint if placeholders remain!

9. Link GitHub Issues

If your project tracks issues via GitHub, link them to the sprint:

Important: "refs" vs "Fixes"

  • refs #17 - Links commit to issue (NO auto-close) - use during development
  • Fixes #17, Closes #17, Resolves #17 - AUTO-CLOSES issue when merged - use in final commit

Manual linking:

jq '.github_issues = [17, 42]' ${SPRINT_STATE_DIR:-.sprint-state}/sprint_<id>.json > tmp && mv tmp ${SPRINT_STATE_DIR:-.sprint-state}/sprint_<id>.json

10. ALWAYS Hand Off to sprint-executor

CRITICAL: After creating an approved sprint plan, ALWAYS hand off to sprint-executor immediately.

Optional: Commit before handoff:

git add ${DESIGN_DOCS_DIR:-design_docs}/planned/M-<milestone>.md
git add ${SPRINT_STATE_DIR:-.sprint-state}/sprint_<id>.json
git commit -m "Add M-<milestone> sprint plan with JSON progress tracking"

Analysis Framework

Design Doc Analysis Checklist

  • Current status: What's done vs pending
  • Timeline: Days/weeks remaining, velocity metrics
  • Priority matrix: Critical vs nice-to-have
  • Deferred items: Features pushed to later versions
  • Technical debt: Known issues or limitations

Implementation Analysis Checklist

  • CHANGELOG: Recent features, LOC counts, test counts
  • Git history: Actual work done (not just documented)
  • Test files: Coverage, test counts, test patterns
  • Code files: Actual implementation, not just stubs
  • TODO/FIXME: Inline comments about future work

Gap Analysis Checklist

  • Features in design doc but not implemented
  • Features implemented but not in design doc
  • Estimated LOC vs actual LOC (for velocity)
  • Planned vs actual timeline
  • Test coverage gaps
  • Documentation gaps

Resources

Sprint Plan Template

See resources/sprint_plan_template.md for complete sprint plan structure.

Best Practices

1. Be Conservative with Estimates

  • Use actual velocity from recent work
  • Add 20-30% buffer for unknowns
  • Don't promise more than recent velocity suggests

2. Prioritize Ruthlessly

  • Focus on highest-value items first
  • Don't try to do everything in one sprint
  • Defer nice-to-haves to future sprints

3. Make Tasks Concrete

  • Bad: "Implement X" is too vague
  • Good: "Write parser for X syntax (~100 LOC) + 15 test cases" is concrete
  • Each task should be achievable in 1 day or less

4. Consider Technical Debt

  • Don't just add features, also fix issues
  • Balance new work with quality improvements
  • Factor in time for bug fixes and refactoring

5. Plan for Testing

  • Every feature needs tests
  • Test LOC is usually 30-50% of implementation LOC
  • Include test writing in timeline estimates

6. Document Assumptions

  • Make implicit assumptions explicit
  • Note areas of uncertainty
  • Highlight where you need user input

7. Verify Design Doc Has Systemic Analysis

Before planning a sprint for a bug fix, verify the design doc addresses systemic issues.

Quick check: Does the design doc mention:

  • Search for similar code paths performed?
  • Other types/cases checked for same gap?
  • Unified fix covering all cases (not just reported one)?

If not: Ask user to revise design doc before planning sprint.

Output Format

See resources/sprint_plan_template.md for full template.

Key sections:

  • Summary (goal, duration, risk level)
  • Current status analysis (completed, velocity, remaining)
  • Proposed milestones (with tasks, criteria, risks)
  • Success metrics
  • Dependencies and open questions

Progressive Disclosure

This skill loads information progressively:

  1. Always loaded: This SKILL.md file (YAML frontmatter + workflow)
  2. Execute as needed: Scripts in scripts/ (velocity analysis)
  3. Load on demand: resources/sprint_plan_template.md (template)

Scripts execute without loading into context window, saving tokens.

Notes

  • This skill is interactive - expect back-and-forth with user
  • Sprint plans should be realistic, not aspirational
  • Use actual data (velocity, LOC counts) over guesses
  • Update design docs as reality diverges from plan
  • Don't commit plan until approved by user